Utah Transit Authority header
File #: 22-265   
Type: Resolution Status: Passed
In control: Board of Trustees
On agenda: 6/22/2022 Final action: 6/22/2022
Title: R2022-06-04 - Resolution Authorizing Execution of Amendment Number 3 to an Interlocal Cooperation Agreement with the Redevelopment Agency of Salt Lake City for the Cooperative Construction of a TRAX Station at 650 South Main Street
Attachments: 1. R2022-06-04 - Resolution Authorizing Execution of Amendment Number 3 to an Interlocal Cooperation Agreement with the Redevelopment Agency of Salt Lake City for the Cooperative Construction of a TRAX Station at 650 South Main Street, 2. Presentation-R2022-06-04

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

David Osborn, Project Manager

 

 

 

TITLE:                                                                                                                                                                         

title

R2022-06-04 - Resolution Authorizing Execution of Amendment Number 3 to an Interlocal Cooperation Agreement with the Redevelopment Agency of Salt Lake City for the Cooperative Construction of a TRAX Station at 650 South Main Street

end

 

AGENDA ITEM TYPE:                                                                                                                        

Resolution

RECOMMENDATION:                                                                                                                       

Approve Resolution R2022-06-04 authorizing Amendment No. 3 for the Interlocal Cooperative Agreement (ILA) with the Redevelopment Agency of Salt Lake City to extend the contract to September 30, 2022 for the TRAX Station at 650 South Main Street.                      

BACKGROUND:                                                                                                                                 

On December 16, 2020 the Board approved resolution R2020-12-12 authorizing the ILA /Cooperative Construction Agreement with Salt Lake City Redevelopment Agency (SLCRDA) for the construction of the 600 South Main Street TRAX Station.  A resolution R2021-07-01 for Amendment No. 1  was approved by the Board on July 14, 2021 with the initial construction bid and schedule.  A resolution R2022-03-07 for Amendment No. 2 was approved by the Board on March 23, 2022 to extend the milestone completion dates to June 30, 2022 due to unanticipated supply chain issues.

DISCUSSION:                                                                                                                                      

This Amendment No .3 is to extend the milestone completion dates for the project in the ILA’s Exhibit B.  Continued supply chain issues have necessitated the need for additional time to complete the project.

Milestone completion dates are being extended as shows in the tables below:

 

 

 

 

 

Current Construction Milestone Dates Contained in Exhibit B

 

Construction*

 

 

Mobilization

7/28/2021

7/29/2021

Construct Platform

7/29/2021

6/30/2022

Install Artwork

3/31/2021

6/30/2022

Startup Testing

4/30/2022

6/30/2022

Punchlist

4/30/2022

6/30/2022

 

 

 

Operation

 

 

Opening Day

 

No later than 6/30/2022

 

 

New Construction Milestone Dates contained in updated Exhibit B as a result of Amendment No.3:

 

Construction*

 

 

Mobilization

7/28/2021

7/29/2021

Construct Platform

7/29/2021

8/31/2022

Install Artwork

3/31/2021

8/31/2022

Startup Testing

6/30/2022

8/31/2022

Punchlist

7/30/2022

9/30/2022

 

 

 

Operation

 

 

Opening Day

 

No later than 9/30/2022

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Salt Lake City

Contract Number:                          

R2020-12-12 ILA

Base Contract Effective Dates:     

12/16/2020-12/15/2021

Extended Contract Dates:            

12/16/2020-09/30/2022

Existing Contract Value:                

$2,502,404

Amendment Amount:                   

$0

New/Total Contract Value:

$2,502,404

Procurement Method:                  

N/A

Budget Authority:                            

No additional funding required

 

 

ALTERNATIVES:                                                                                                                                    

If this amendment does not move forward, Utah Transit Authority is at risk of not completing the construction and opening the new platform within the timeframe of the agreement.

FISCAL IMPACT:                                                                                                                                

The project construction is funded in the 2022 budget and this contract will cover that funding. There is no additional funding required for this Amendment No. 3

ATTACHMENTS:                                                                                                                                

                     Resolution R2022-06-04