File #: 21-506   
Type: Resolution Status: Passed
In control: Board of Trustees
On agenda: 1/12/2022 Final action: 1/12/2022
Title: R2022-01-02 - Resolution Authorizing Execution of Supplement No. 3 to an Interlocal Cooperation Agreement with West Valley City for the West Valley Bike Lane Project as Part of the TIGER First/Last Mile Program.
Indexes: Finance - Grants, Governance - Government Agencies / Political Subdivisions
Attachments: 1. R2022-01-02_Resolution_Authorizing_Execution_of_Supplement_No._3, 2. Presentation-R2022-01-02
Related files: 21-187

TO:                

Board of Trustees

THROUGH:  

Mary DeLoretto, Interim Executive Director

FROM:          

Dave Hancock, Acting Chief Service Development Officer

PRESENTER(S):

Grey Turner, Manager Civil Engineering and Design

 

Dave Hancock, Acting Chief Service Development Officer

                                                                  

TITLE:                                                                                                                                                                         

title

R2022-01-02 - Resolution Authorizing Execution of Supplement No. 3 to an Interlocal Cooperation Agreement with West Valley City for the West Valley Bike Lane Project as Part of the TIGER First/Last Mile Program.

end

 

AGENDA ITEM TYPE:                                                                                                                        

Resolution

RECOMMENDATION:                                                                                                                       

Approve Resolution R2022-01-02 authorizing Supplement No. 3 to the West Valley Interlocal Cooperation Agreement (ILA) to provide additional funds for the West Valley Bike Lane Project as part of the TIGER First/Last Mile Program.                       

BACKGROUND:                                                                                                                                 

TIGER Stakeholder Agreement and Supplement No. 1 between UTA and West Valley City (Stakeholder Agreement 18-2656BM) were executed on March 30, 2018 between UTA and West Valley City for the Bike Lane Project as part of the TIGER First/Last Mile Program with a total budget of $1,721,308, of which $1,377,046 was from TIGER grant funding and $344,262 was matching funds provided by West Valley City.  Supplement No. 2 (R2021-06-05, June 2021) was to increase the budget of the West Valley Bike Lane Project by $1,932,024.65, of which, additional local funds were provided by West Valley City.

Supplement No. 3 is to increase the budget of the West Valley Bike Lane Project by $154,369.17. This additional funding is being provided by West Valley City. The total West Valley Bike Lane Project budget with Supplement No. 3 will be $3,807,701.82.

This request is seeking approval of Supplement No. 3 to be issued this time.

 

 

DISCUSSION:                                                                                                                                      

The additional funding is required for construction of the West Valley Bike Lane Project under the TIGER First/Last Mile Grant Project. West Valley City will be invoiced for Supplement No. 3 City participation funds ($154,369.17) upon execution of Supplement No. 3.

ALTERNATIVES:                                                                                                                                    

Without the additional funding, there would not be enough budget to pay for the construction phase 2 of the West Valley Bike Lane Project improvements at the city’s request.

FISCAL IMPACT:                                                                                                                                

The additional West Valley City local project partner funding will increase the overall TIGER Grant Project Budget by $154,369.17. The additional funds were not included in the original 2021 TIGER project budget. They will be incorporated into the 2022 Capital budget at a future date as needed.

ATTACHMENTS:                                                                                                                                

R2022-02-02 - Approving West Valley City Interlocal Cooperative Agreement Supplement No. 3