File #: 24-03868   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 12/4/2024 Final action: 12/4/2024
Title: Contract: Depot District CNG Fueling Bay Addition Design (FFKR Architects)
Attachments: 1. Contract: Depot District CNG Fueling Bay Addition Design (FFKR Architects)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Dave Hancock, Chief Capital Services Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Design & Construction

 

Ethan Ray, Project Manager II

 

TITLE:                                                                                                                                                                         

title

Contract: Depot District CNG Fueling Bay Addition Design (FFKR Architects)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the executive director to execute the contract and associated disbursements with FFKR Architects in the amount of $288,275 for the Depot District CNG Fueling Bay Addition Design and a construction support option, to be exercised in UTA’s sole discretion, in the amount of $127,652 for a total contract value of $415,652                     

BACKGROUND:                                                                                                                                 

UTA was awarded a Low or No Emission Grant to add 25 compressed natural gas (CNG) buses to the fleet. These buses will be housed at the Central Depot District Garage and will operate on the 5600 West Bus Route. In order to support these buses, additional CNG fueling capacity is needed. The Depot District CNG fueling building was master-planned for expansion when it was built in 2015.

DISCUSSION:                                                                                                                                      

UTA issued a request for qualifications for an architecture & engineering firm to design an additional fueling bay equipped with a CNG dispenser and other ancillary equipment to be added to the existing Central Depot District Garage. FFKR Architects was selected through this procurement process. The contract includes the preparation of construction documents for the expansion with optional construction phase services.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

FFKR Architects

Contract Number:                          

24-03868

Base Contract Effective Dates:     

December 2024 to December 2025

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$288,275.00 for the design phase and $127,377 for the construction support option if exercised, totaling $415,652.00

Procurement Method:                  

Request for Qualifications (RFQu)

Budget Authority:                            

2024 Approved Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

UTA can choose to go with one of the other firms that bid on the project.  Not moving forward with the expansion of the CNG fueling building would negatively impact UTA’s ability to operate the new CNG buses.

FISCAL IMPACT:                                                                                                                                

The base contract has a Not to Exceed value of $288,275. There is an option for Construction Phase Services of $127,377, for a total contract value of $415,652 if option is exercised.

The funding for this project is coming from external sources including the Low-No grant, UDOT TTIF funding, and a Congestion Mitigation and Air Quality (CMAQ) grant. It is included in the 2024 Approved Capital Budget and 5-year Capital Plan (MSP260 - Westside Express).

Available 2024 Capital Budget: $812,543

2025 Capital Plan: $16.5 million

2026 Capital Plan $15 million

2027 Capital Plan $8.12 million

ATTACHMENTS:                                                                                                                                

Contract: 24-03868VW Depot District CNG Fueling Bay Addition Design