Legislation Details

File #: 17794   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 4/22/2026 Final action: 4/22/2026
Title: Contract: Above Ground Storage Tanks Product Line Replacement (Spackman Enterprises LLC)
Attachments: 1. Purchase Order: Above Ground Storage Tanks Product Line Replacement (Spackman Enterprises LLC)

TO:                

Board of Trustees

FROM:          

Jon Larsen, Chief Capital Services Officer

PRESENTER(S):

David Osborn, Project Manager

 

 

TITLE:                                                                                                                                                                         

title

Contract: Above Ground Storage Tanks Product Line Replacement (Spackman Enterprises LLC)

end

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Purchase Order 17794 under Utah State contract MA4744 for above ground storage tanks product line replacement with Spackman Enterprises LLC in the amount of $294,865.                     

BACKGROUND:                                                                                                                                 

In 2022, the legislature passed a law regulating above ground petroleum storage tanks (APST) with underground product lines.  The Riverside Service Center is subject to this regulation and required to make improvements to meet the updated requirements.

DISCUSSION:                                                                                                                                      

UTA staff are requesting approval of Purchase Order 17794 with Spackman Enterprises LLC to replace the underground product lines. The new lines will be compliant with current regulations and replace lines that are past their useful life.

CONTRACT SUMMARY:

 

Contractor Name

Spackman Enterprises LLC

Contract Number

Utah State Contract: MA4744

 

Purchase Order: 17794

Contract Start/End Dates

November 11, 2024 - November 11, 2029

 

Purchase Order: April 22, 2026 - November 30, 2026

Total Contract Value

$294,865

Procurement Method

State Contract

Budget Authority

Approved 2026 Capital Budget

ALTERNATIVES                                                                                                                                  

Discontinue use of the lines and find an alternative to convey oil and products from the above ground storage tanks to the building for use in vehicles.

FISCAL IMPACT:

The 2026 amount is included in the 2026 capital project budget for FMA702 ($320,000).

                     2026 Contract Total: $294,865 Account # 40-1702.63000.3002

Funding Sources:

                     Grant funds: $256,000

                     UTA Funds: $64,000

ATTACHMENTS:                                                                                                                                

                     Purchase Order: Above Ground Storage Tanks Product Line Replacement (Spackman Enterprises LLC)

                     State Contract MA4744 (Link: <https://bit.ly/USC_MA4744>)