Legislation Details

File #: 23-036853VW   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 6/14/2023 Final action: 6/14/2023
Title: Contract: Master Task Ordering Agreement for Bus System Enhancement Design Services Consultant Pools A, B, C (Kimley-Horn and Associates, Inc.)
Attachments: 1. Contract_MTOA for Bus System Enhancement Design Services (Kimley-Horn)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Capital Services Officer

PRESENTER(S):

Dave Hancock, Director of Capital Development

 

Travis Colledge, Project Manager III

 

TITLE:                                                                                                                                                                         

title

Contract: Master Task Ordering Agreement for Bus System Enhancement Design Services Consultant Pools A, B, C (Kimley-Horn and Associates, Inc.)

end

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Authorize the Executive Director to execute the bus system enhancement Master Task Ordering Agreement, and associated disbursements, with Kimley-Horn and Associates, Inc. for one year with a not-to-exceed amount of $500,000.                                           

BACKGROUND:                                                                                                                                 

In the 2023-2027 Five-year Capital Plan, local funding has been allocated yearly for Bus Stops, End of Line Facilities, and Operator Restrooms.  To develop an ongoing yearly program of projects for bus system improvements, Design Pools A, B, and C were developed. Maintaining a pool of pre-qualified consultants that may be solicited to complete tasks via task order will increase UTA’s efficiency to deliver system enhancement projects yearly and utilize the programmed budget. Since requirements and budget are determined on an annual basis, these contracts are for one year with 4 additional one-year options to be exercised each year contingent on the availability of funds.  Board approval will be obtained prior to the exercise of each option provided its value exceeds $200,000.

DISCUSSION:                                                                                                                                      

If approved, Kimley-Horn and Associates, Inc. is qualified for Design Pools A, B, and C:

                     Pool A-Bus Stops $300,000 for one year

                     Pool B-End of Line (EOL) Facilities $100,000 for one year

                     Pool C-Operator Restrooms $100,000 for one year

 

No work is authorized, nor funds obligated until a task order is issued under this contract. Individual task orders totaling $200,000 or more will be brought to the board for approval. If the cost of all task orders issued for year one under this agreement exceeds the not-to- exceed Amount of $500,000, additional board approval will be required.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Kimley-Horn and Associates, Inc.

Contract Number:                          

23-036853 VW

Base Contract Effective Dates:     

6/14/2023 to 6/14/2024

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$500,000  ( Not to Exceed Amount for pools A, B, & C)

Procurement Method:                  

RFQu (Qualification)

Budget Authority:                            

2023Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

By not developing a pool of consultants for design services, UTA is compromised in its ability to deliver system enhancement projects. The alternative to executing contracts for design services in each pool category would require three RFQu’s for design services every year and create additional work while possibly impacting completion dates.  The current approach streamlines the process, allows for more efficient delivery, and helps ensure the project gets completed on time.

FISCAL IMPACT:                                                                                                                                

The 2023 Capital Budget includes fund for these busy system enhancement design services.

 