File #: 18-2741-05   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 8/10/2022 Final action: 8/10/2022
Title: Change Order: Depot District Clean Fuels Technology Center Contract Change Order No. 28 - Phase 5 On Site Underground Power Conduits and Vaults (Big D Construction)
Attachments: 1. Big-D CO #28 GMP-5 MSP102

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

David Osborn, Project Manager

 

TITLE:                                                                                                                                                                         

title

Change Order: Depot District Clean Fuels Technology Center Contract Change Order No. 28 - Phase 5 On Site Underground Power Conduits and Vaults (Big D Construction)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute  change order No 28 and associated disbursements with Big D Construction in the amount of $719,343                      

BACKGROUND:                                                                                                                                 

In June 2018, UTA released a request for procurement (RFP) for the construction of the Depot District Clean Fuels Technology Center. This facility will replace the existing aging and undersized Central bus facility and will house up to 150 alternative and standard fuel buses with the ability to expand to 250 buses in the future. Rocky Mountain Power requires UTA to install underground conduit and vaults so they can provide wiring and equipment to provide the necessary power for the new facility.

DISCUSSION:                                                                                                                                      

This change order is to provide underground conduit and vaults from the existing overhead power lines near 400 South to the existing electrical gear on the west side of the parking lot west of the new Depot District Building. There will be a future change order to install conduits and vaults from the parking lot out to 200 South and along 200 South to 600 West. A Direction or Authorization to Proceed (DAP) has been issued in the amount of $109,100 to order the precast concrete vaults which take a minimum of 6 weeks to deliver to the site.

 

 

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Big D Construction

Contract Number:                          

18-2741TP-28

Base Contract Effective Dates:     

August 24, 2018 (Phase 1 contract) June 24, 2019 (Phase 2 contract)

Extended Contract Dates:            

March 10, 2023

Existing Contract Value:                

$73,337,107

Amendment Amount:                   

$719,343

New/Total Contract Value:

$74,056,450

Procurement Method:                  

Change Order

Budget Authority:                            

Approved Depot District Project Budget

 

 

ALTERNATIVES:                                                                                                                                    

If this change order is not approved, Rocky Mountain Power will not be able to provide sufficient power for the new facility.

FISCAL IMPACT:                                                                                                                                

The budget is included in the Depot District project which is included in the 5-year Capital Plan.

ATTACHMENTS:                                                                                                                                

                     Change order with Big D Construction