Legislation Details

File #: 20-03382-23-018   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 7/26/2023 Final action: 7/26/2023
Title: Change Order: On-Call Systems Maintenance Contract Task Order #23-018 - S-Curve Negative Return Cable-to-Rail Connections (Rocky Mountain Systems Services)
Attachments: 1. Change Order_On-Call Systems Maintenance TO #23-018

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Capital Services Officer

PRESENTER(S):

Dean Hansen, Systems Engineering Manager

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Systems Maintenance Contract Task Order #23-018 - S-Curve Negative Return Cable-to-Rail Connections (Rocky Mountain Systems Services)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve task order #23-018 (S-Curve Negative Return Cable-to-Rail Connections) to on-call systems maintenance contract with Rocky Mountain System Services (RMSS) and authorize the Executive Director to execute task order and associated disbursements in the amount of $289,839.                                          

BACKGROUND:                                                                                                                                 

In March of 2021, UTA executed contract 20-03382VW with Rocky Mountain Systems Services (RMSS) for on-call systems maintenance. The term of this contract is for three years with two one-year term options. RMSS was selected based on best value procurement methodology. The UTA Board of Trustees approved the contract on February 24, 2021, and it was fully executed on March 2, 2021. On November 18, 2022, UTA executed change order #23-001 to exercise the two, one-year term options, ending on December 31, 2025. The original contract value was estimated at $15,000,000. On April 12, 2023, the UTA Board of Trustees approved an increase of the estimated contract value to $30,000,000.

Typical task orders under this contract include:

                     Support for rail and maintenance of way systems

                     Upgrades, repairs, analysis, and training of train control systems

                     Monitoring and analysis of stray current

                     Repair, maintenance, and training of overhead contact systems and traction power substations

                     Inspection, connection, repair, of traffic signals

DISCUSSION:                                                                                                                                      

UTA is requesting approval of task order #23-018 with RMSS. This task order replaces welded negative return cable-to-rail connections with bolted connections on ballasted and embedded track. Replacing these connections eliminates the need to use welding equipment when a connection breaks, which reduces the amount of time the track is out of service.

Location of Ballasted Track Connections:

                     SRN13: 9400 S. Substation

                     SRR12: Rio Grande Substation

                     SRS11: Sugar Highway Substation

                     SRA10: Atwood Substation

                     SRP9: Pallas Yard Substation

                     SRM8: Murray Substation

                     SRC7: Central Substation

                     SRW6: Walton Substation

                     SRB4: Burton Substation

Location of Embedded Track Connections:

                     900 E. 400 S.

                     1000 E. 500 S.

                     1200 E. 500 S.

                     1300 E. 500 S.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Rocky Mountain Systems Services

Contract Number:                          

20-03382-23-018

Base Contract Effective Dates:     

March 2, 2021, through December 31, 2023

Extended Contract Dates:            

through December 31, 2025

Existing Contract Value:                

$21,219,373

Amendment Amount:                   

$289,839

New/Total Contract Value:

$21,509,212

Procurement Method:                  

Task Order Issued under Master Task Order Agreement

Budget Authority:                            

2023-2027 Capital Plan through the Rail Switch and Trackwork Rehab/Replacement Project

 

 

ALTERNATIVES:                                                                                                                                    

Disapprove task order. Continue to suspend revenue services to repair cable-to-rail connection breaks.

FISCAL IMPACT:                                                                                                                                

This budget is included in the 2023-2027 Capital Plan.

ATTACHMENTS:                                                                                                                                

Task Order #23-018