Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 2/14/2024 Final action: 2/14/2024
Title: Change Order: On-Call Systems Maintenance Contract Task Order #24-010 - Materials for Rice Interlocking Wayside System Upgrade (Rocky Mountain Systems Services)
Attachments: 1. Change Order: On-Call Systems Maintenance Contract Task Order #24-010 - 2024 Rice Interlocking Materials (Rocky Mountain Systems Services)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Dave Hancock, Chief Service Development Officer

PRESENTER(S):

Dean Hansen, Manager Systems Engineering

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Systems Maintenance Contract Task Order #24-010 - Materials for Rice Interlocking Wayside System Upgrade (Rocky Mountain Systems Services)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve task order #24-010 (Rice Interlocking Materials) to on-call systems maintenance contract with Rocky Mountain System Services (RMSS) and authorize the Executive Director to execute task order and associated disbursements in the amount of $433,154.                     

BACKGROUND:                                                                                                                                 

In March of 2021, UTA executed contract 20-03382VW with Rocky Mountain Systems Services (RMSS) for on-call systems maintenance. The term of this contract is for three years with two one-year term options. RMSS was selected based on best value procurement methodology. The UTA Board of Trustees approved the contract on February 24, 2021, and it was fully executed on March 2, 2021. On November 18, 2022, UTA executed change order #23-001 to exercise the two, one-year term options, ending on December 31, 2025. The original contract value was estimated at $15,000,000. On April 12, 2023, the UTA Board of Trustees approved an increase of the estimated contract value to $30,000,000.

Typical task orders under this contract include:

                     Support for rail and maintenance of way systems

                     Upgrades, repairs, analysis, and training of train control systems

                     Monitoring and analysis of stray current

                     Repair, maintenance, and training of overhead contact systems and traction power substations

                     Inspection, connection, repair, of traffic signals

DISCUSSION:                                                                                                                                      

UTA is requesting approval of task order #24-010 with RMSS. This task order is for the procurement of long-lead materials to upgrade the wayside system at the Rice interlocking to ElectroLogIXS with train detecting circuits and powered switch machines. See task order attachments for a list of materials.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Rocky Mountain Systems Services

Contract Number:                          

20-03382-24-010

Base Contract Effective Dates:     

March 2, 2021, through December 31, 2023

Extended Contract Dates:            

Through December 31, 2025

Existing Contract Value:                

$25,511,607.96 *Note: a calculation error was made after TO 23-18 which caused the existing and total contract values to be off for all TO’s presented on 12/20/2023.  This existing contract value has been verified as correct.

Amendment Amount:                   

$433,154

New/Total Contract Value:

$25,944,761.96

Procurement Method:                  

RFP best value modification

Budget Authority:                            

2024 Capital Budget - Rail Switches and Trackwork Rehab and Replacement Project (SGR-404)

 

 

ALTERNATIVES:                                                                                                                                    

Disapprove task order. Not ordering long-lead materials will delay construction.

FISCAL IMPACT:                                                                                                                                

Budget for Task Order 24-010 amendment value of $433,154 is included in the 2024-2028 Capital Plan.

ATTACHMENTS:                                                                                                                                

Task Order #24-010