Legislation Details

File #: 20-03382-16   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 11/10/2021 Final action: 11/10/2021
Title: Change Order: On-Call Systems Maintenance - Task Order #016 - Mandatory Directive Expedient Release (MDER) Design and Installation in Vineyard Area (Rocky Mountain Systems Services)
Attachments: 1. On-Call Systems Maintenance - Task Order #016 - Mandatory Directive Expedient Release (MDER) Design and Installation in Vineyard Area (Rocky Mountain Systems Services)

TO:                

Board of Trustees

THROUGH:  

Mary DeLoretto, Interim Executive Director

FROM:          

David Hancock, Acting Chief Service Development Officer

PRESENTER(S):

David Hancock, Acting Chief Service Development Officer

 

Jared Scarbrough, Acting Director of Capital Construction

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Systems Maintenance - Task Order #016 - Mandatory Directive Expedient Release (MDER) Design and Installation in Vineyard Area (Rocky Mountain Systems Services)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve task order #016 to on-call systems contract and authorize Executive Director to execute task order and associated disbursements with Rocky Mountain Systems Services (RMSS) in the amount of $382,814.                     

BACKGROUND:                                                                                                                                 

In November 2020, UTA released a request for procurement (RFP) for an on-call maintenance contractor focused specifically on systems engineering and maintenance support. Rocky Mountain Systems Services was selected as the winner based on overall scoring using the best value format. The UTA Board of Trustees approved the contract and authorized the Executive Director to execute the contract with RMSS on February 24, 2021. This contract is for three-years with two, one-year options. Typical task orders under this contract include:

Subject matter experts to support UTA rail systems and MOW systems

departments.

Train Control System upgrades, repairs, analysis, and training

Stray Current monitoring and analysis

OCS/TPSS repair, maintenance, and training

Traffic Signal inspections, connections, repairs, and coordination

 

 

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval of Task Order #016 with RMSS to complete the Mandatory Directive Expedient Release (MDER) project in the Vineyard area. UTA is designing and installing MDER functionality at the Grade Crossings along the Frontrunner Alignment. Currently, there is an on-going project in the Vineyard area preventing the MDER contractors from designing and constructing in that area. UTA has postponed the MDER work in the Vineyard area and removed that scope from the Positive Train Control (PTC) project contract (UT14-17TH) via a deductive change order. Completing this Task Order will aid in closing out the UT14-17TH contract this year, as planned.

Task Order #016 will require that the contractor follow the original scope of work for the MDER project and apply all necessary software, hardware, and testing in the following (8) locations:

                     400 South Orem

                     1600 North Vineyard

                     1100 South American Fork

                     1500 South American Fork

                     100 East American Fork

                     100 West American Fork

                     Storrs Ave. American Fork

                     200 South American Fork

Work for Task Order #016 will begin after the completion of the on-going construction in the Vineyard area.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Rocky Mountain Systems Services

Contract Number:                          

20-03382VW-16

Base Contract Effective Dates:     

February 24, 2021 through December 31, 2023

Extended Contract Dates:            

N/A

Existing Contract Value:                

$2,918,412

Amendment Amount:                   

$382,814

New/Total Amount Contract Value:

$3,301,226

Procurement Method:                  

RFP best value modification

Funding Sources:                            

Funding Sources: 2021 SGR Budget

 

 

ALTERNATIVES:                                                                                                                                    

The do-nothing alternative would mean that this portion of track in the Vineyard area would have no MDER functionality. It is important to note that this task was previously included in the PTC project but had to be postponed.

FISCAL IMPACT:                                                                                                                                

This budget is included in the 2021 Capital Program.

ATTACHMENTS:                                                                                                                                

1) Contract