Type: Procurement Contract/Change Order Status: Agenda Ready
In control: Board of Trustees
On agenda: 10/22/2025 Final action:
Title: Change Order: Light Rail Vehicles Change Order 1 - Notice to Proceed in Exercising Option to Purchase 20 Vehicles (Stadler US)
Attachments: 1. Change Order: Light Rail Vehicles Change Order 1 – Notice to Proceed in Exercising Option to Purchase 20 Vehicles (Stadler US)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Jared Scarbrough, Acting Chief Capital Services Officer

PRESENTER(S):

Kyle Stockley, Director of Capital Vehicles

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Light Rail Vehicles Change Order 1 - Notice to Proceed in Exercising Option to Purchase 20 Vehicles (Stadler US)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order 1 and associated disbursements on contract 23-03791 with Stadler US, in the amount of $121,511,694, on the notice to proceed to exercise the option to acquire an additional 20 new light rail vehicles and associated spare parts.                     

BACKGROUND:                                                                                                                                 

On October 23, 2024, the Board of Directors approved a contract with Stadler US for the manufacture and delivery of 20 new light rail vehicles and their associated spare parts. The contract includes UTA-controlled options for procurement of up to an additional 60 vehicles at a guaranteed contract price.

DISCUSSION:                                                                                                                                      

UTA’s existing SD100/SD160 light rail vehicles are coming to the end of their useful life. In October 2024, the base order contract was executed for procurement of 20 replacement light rail vehicles.

In the past year, UTA staff has identified additional funding for the procurement of an additional 20 vehicles to continue the replacement effort of the retiring SD100/SD160 fleet. The additional vehicles are required to continue to replace the retiring SD100/SD160 fleet and enable level-boarding throughout the system.

 

The contract pricing for these optional vehicles was set when the base order was placed and was been determined to be fair and reasonable based the UTA independent cost estimate and the performance of a price analysis.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stadler US

Contract Number:                          

23-03791-01

Base Contract Effective Dates:     

October 24, 2024 to October 24, 2031

Extended Contract Dates:            

N/A

Existing Contract Value:                

$129,300,194

Amendment Amount:                   

$121,511,694

New/Total Contract Value:

$250,811,888

Procurement Method:                  

RFP

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

The alternative to moving forward with this contract would be to forego the purchase of the 20 new low-floor light rail vehicles. However, this option would prevent UTA from meeting its commitment to provide a fully level-boarding light rail system.

FISCAL IMPACT:                                                                                                                                

This contract is for procurement and delivery of vehicles and spare parts to be completed over the next 5 years from 2025 through 2029. The additional planned expenditures are as follows:

                     2025 Change Order Total: $60,000,000

                     2026 Change Order Total: $0

                     2027 Change Order Total: $0

                     2028 Change Order Total: $36,000,000

                     2029 Change Order Total: $25,511,694

 

Total Change Order Value: $121,511,694

Contract Total: $250,811,888