Title: Utah Transit Authority Draft 2022-2026 Five-Year Capital Plan
Attachments: 1. Utah Transit Authority Draft 2022-2026 Five-Year Capital Plan, 2. Presentation-Capital Projects- UTA Draft 2022-2026 Five Year Capital Plan
Related files: 21-429

TO:                

Local Advisory Council

THROUGH:  

Mary DeLoretto, Interim Executive Director

FROM:          

David Hancock, Acting Chief Service Development Officer

PRESENTER(S):

Bill Greene, Chief Financial Officer

 

David Hancock, Acting Chief Service Development Officer

 

Dan Hofer, Manager Capital Assets and Project Controls

 

TITLE:                                                                                                                                                                         

title

Utah Transit Authority Draft 2022-2026 Five-Year Capital Plan

end

 

AGENDA ITEM TYPE:                                                                                                                        

LAC - Consultation

RECOMMENDATION:                                                                                                                       

Discuss Agency’s Draft 2022-2026 Five-Year Capital Plan and receive input from the Advisory Council Members                       

BACKGROUND:                                                                                                                                 

UTA’s 5-year Capital Plan is required to be updated every year, per the UTA Board of Trustees Policy 2.1 Financial Management. The 5-year Capital Plan includes all construction, capital improvements, major equipment purchases, and other special projects requiring expenditures over $25,000. This includes projects that are funded partially or fully by outside funding sources, such as grants or local partners.

The plan is required to be financially constrained and maintain assets at a state of good repair to protect UTA’s capital investments and minimize future maintenance and replacement costs. Five-year forecasts help mitigate the challenges of applying a one-year budget to multi-year projects and support long-range financial planning and prudent management of the enterprise.

This current draft 5-Year Capital Plan covers the period from 2022 through 2026.

DISCUSSION:                                                                                                                                      

Staff will present the proposed draft 5-year Capital Plan for 2022 through 2026 for review and discussion. As project delivery schedules are updated, and carryover forecasts are determined, it is anticipated that the draft plan will be refined and updated to reflect Board and LAC input, as well as the carryover forecasts. The updated 5-Year Capital Plan will be brought back to the Advisory Council and Board of Trustees later this fall for review and final adoption.

ALTERNATIVES:                                                                                                                                    

N/A

FISCAL IMPACT:                                                                                                                                

Once the UTA Board approves the final 5-year Capital Plan, the proposed capital budget for fiscal year 2022 will be incorporated into UTA’s proposed 2022 overall budget. The 5-year capital plan will support the overall 5-year financial plan.