File #: 24-03813-14   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 5/14/2025 Final action: 5/14/2025
Title: Change Order: Construction Services Agreement for Jordan River Bldg #2 Remodel Change Order 14 - Secure Walls and Bracing (Paulsen Construction, LLC)
Attachments: 1. Change Order 14 - Secure Walls And Bracing (Paulsen Construction, LLC)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Services Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Design & Construction

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Construction Services Agreement for Jordan River Bldg #2 Remodel Change Order 14 - Secure Walls and Bracing (Paulsen Construction, LLC)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order Number 14 and associated disbursements with Paulsen Construction, LLC in the amount of $905,674.98.                     

BACKGROUND:                                                                                                                                 

On May 22, 2024, the UTA Board of Trustees approved contract 24-03813 with Paulsen Construction, LLC to remodel Jordan River #2, which is an existing building owned by UTA and has been mostly vacant and used as overflow warehouse space.

DISCUSSION:                                                                                                                                      

Execution of this change order will allow Paulsen Construction, LLC to provide strapping and bracing of the current structure to provide more stability to the existing structure. UTA staff is requesting approval to execute Change Order No. 14 in the amount of $905,674.98 on the Paulsen Construction, LLC contract for the Jordan River #2 project.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Paulsen Construction, LLC

Contract Number:                          

24-03813

Base Contract Effective Dates:     

May 31, 2024 - March 31, 2026

Extended Contract Dates:            

N/A

Existing Contract Value:                

$8,063,587.96

Amendment Amount:                   

$905,674.98

New/Total Contract Value:

$8,969,262.94

Procurement Method:                  

RFP - Best Value

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

The alternative would be to do nothing. It is not a code requirement to perform these upgrades. The building can still function as intended. This improvement would help the building to perform better in a seismic event.

FISCAL IMPACT:                                                                                                                                

The approved 2025 Capital Budget includes a budgeted amount of $7,380,000 from the SGR390 Jordan River #2 Remodel - capital project, which are lease funds.

2025 Change Order Total: $905,674.98

ATTACHMENTS:                                                                                                                                

                     Change Order 14 - Secure Walls and Bracing (Paulsen Construction, LLC)