Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 4/12/2023 Final action: 4/12/2023
Title: Change Order: Light Rail Red Signal Enforcement System - Change Order #23-002 -Limited Notice-to-Proceed for Phase 2 to Procure Long-Lead Materials (Rocky Mountain Systems Services)
Attachments: 1. Change Order-LR Red Light signal Enforcment CO 002 (RMSS), 2. Contract-LR Red Signal Enforcement Phase 1 (RMSS) 17-2226JH

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

Dean Hansen, Systems Engineering Manager

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Light Rail Red Signal Enforcement System - Change Order #23-002 -Limited Notice-to-Proceed for Phase 2 to Procure Long-Lead Materials (Rocky Mountain Systems Services)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve change order #23-002 (Limited Notice-to-Proceed for Phase 2 to Procure Long-Lead Materials) to the Light Rail Red Signal Enforcement System Phase 1 contract with Rocky Mountain System Services (RMSS) and authorize the Executive Director to execute contract and associated disbursements in the amount of $4,247,949.                     

BACKGROUND:                                                                                                                                 

In July 2017, UTA released a Request for (RFP) for a Construction Manager/General Contactor (CMGC) for Phase 1: Preconstruction Services of the Light Rail Red Signal Enforcement Systems project. RMSS was selected as the winner based on overall scoring using the best value format.  The Executive Director executed the contract with RMSS on April 26, 2018.  Section 8 of the contract allows for an amendment to execute Phase 2: Construction Services, if UTA and RMSS agree on scope and price.  

On November 9, 2018, UTA put the Light Rail Red Signal project on hold to allow the Federal Transit Authority to complete the new Safety Rail Protocols. The contract resumed on September 22, 2022, via a Notice-to-Proceed letter to RMSS. The Phase 1 scheduled completion date was March 11, 2023. On March 8, 2023, the UTA Configuration Control Committee approved a Phase 1 time extension change order (#23-001) through December 31, 2023.

DISCUSSION:                                                                                                                                      

UTA is requesting approval of change order 23-002 with RMSS. This change order executes a Limited Notice-to-Proceed for Phase 2: Construction Services with RMSS to procure long-lead materials during Phase 1: Preconstruction Services. It also approves the procurement of spare onboard materials for the new Light Rail Operations Simulator. The materials/quantities listed below are based on preliminary designs and are consistent with the scope identified in the contract:

Material Description

Quantity

Onboard

Central Unit RSES with 84TE with Fully equipped BGR

79

System Cabling & Electrical Harness

79

Operator Interface Panel

159

Vehicle Magnet w/ mounting hardware

159

Wayside

Wayside Track Magnets

22

Wayside Track Magnet Brackets

24

Vital Relay

21

Vital Relay Base

21

DC/DC Converter (12VDC to 40VDC)

12

Testing Equipment

Rail Magnet (Test Track)

1

Wayside Magnet Teslameter

1

Diagnostic Tool/Windows License

1

Handheld Test Magnet

2

Simulator Onboard

Central Unit RSES with 84TE (482mm/19") rack

2

System Cabling & Electrical Harness

2

Operator Interface Panel

2

Vehicle Magnet w/ mounting hardware

2

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Rocky Mountain Systems Services (RMSS)

Contract Number:                          

17-2226-23-002

Base Contract Effective Dates:     

4/26/2018 (original execution),  9/22/2022-3/11/2023 (Notice to Proceed)-

Extended Contract Dates:            

3/11/2023-12/31/2023 (extended with CO 001)

Existing Contract Value:                

$294,834

Amendment Amount:                   

$4,247,949

New/Total Contract Value:

$4,542,783

Procurement Method:                  

RFP best value modification

Budget Authority:                            

Local funds through the Capital Construction Light Rail Red Signal Enforcement System Project (SGR-370)

 

 

ALTERNATIVES:                                                                                                                                    

Disapprove change order. Not procuring long-lead materials will delay Phase 2: Construction Services by 12-14 months. Additionally, if spare parts are not procured for the Operations Simulator, in the event of an equipment failure, it will be unserviceable. 

FISCAL IMPACT:                                                                                                                                

This budget is included in the 2023-2027 Capital Program.

ATTACHMENTS:                                                                                                                                

Change Order 23-002