Skip to main content
Utah Transit Authority header
File #: 22-03608-04   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 11/12/2025 Final action: 11/12/2025
Title: Change Order: Janitorial Services for all UTA Office and Maintenance Facilities Change Order 4 - Exercising First Option Year and Adding Tooele Location (Merchants Building Maintenance)
Attachments: 1. Change Order: Janitorial Services for all UTA Office and Maintenance Facilities No. Change Order 4 – Exercising First Option Year and Adding Tooele Location (Merchants Building Maintenance)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Andrés Colman, Chief Operations Officer

PRESENTER(S):

Kevin Anderson, Director of Maintenance Support

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Janitorial Services for all UTA Office and Maintenance Facilities Change Order 4 - Exercising First Option Year and Adding Tooele Location (Merchants Building Maintenance)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order No. 4 which exercises the first-year option and adds a Tooele location to the existing contract 22-03608 with Merchants Building Maintenance Corp., who provide janitorial services to all UTA office and maintenance facilities in the amount of $1,155,746.                      

BACKGROUND:                                                                                                                                 

The current Janitorial contract was approved by the Board on December 21, 2022 to cover services for three (3) years with two (2) one-year option periods to continue services.  This contract change order is to exercise the first option year and to add a Tooele location.

DISCUSSION:                                                                                                                                      

UTA Staff are confident that Merchant Building Maintenance will continue to provide UTA with the best janitorial services by exercising the first option year and also adding a new Tooele location. The new contract not-to-exceed total value will be increased to $4,449,314.04. The new option amount of $1,155,746.04 will be partially funded in the 2025 and 2026 Facilities Operations Budget.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

 Merchant Building Maintenance Corp.

Contract Number:                          

 22-03608-04

Base Contract Effective Dates:     

12/22/2022 - 9/30/2025

Extended Contract Dates:            

10/01/2025 - 9/30/2026

Existing Contract Value:                

$3,293,568

Amendment Amount:                   

$1,155,746

New/Total Contract Value:

$4,449,314

Procurement Method:                  

RFP

Budget Authority:                            

Approved 2025 Operating Budget

 

 

ALTERNATIVES:                                                                                                                                    

Prepare a new procurement for janitorial services.

FISCAL IMPACT:                                                                                                                                

The total option amount is included in the Facilities Operations Budget as follows:

                     2025 - Change Order Total: $288,936

                     2026 - Change Order Total: $866,810

Total Change Order not to exceed Value: $1,155,746

Total Contract not to exceed amount: $4,449,314

ATTACHMENTS:                                                                                                                                

                     Change Order: Janitorial Services for all UTA Office and Maintenance Facilities No. Change Order 4 - Exercising First Option Year and Adding Tooele Location (Merchants Building Maintenance)