Skip to main content
Utah Transit Authority header
File #: 24-03849-06   
Type: Procurement Contract/Change Order Status: Agenda Ready
In control: Board of Trustees
On agenda: 4/8/2026 Final action:
Title: Change Order: S-Line Extension Change Order 6 - Phase 1 Deductive Budget Adjustment (Kiewit West Infrastructure Co.)
Attachments: 1. Change Order: S-Line Extension Change Order 6 - Phase 1 Deductive Budget Adjustment (Kiewit West Infrastructure Co.)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                

Board of Trustees

FROM:          

Jon Larsen, Chief Capital Services Officer

PRESENTER(S):

David Osborn, Acting Director of Capital Design and Construction;

 

Ethan Ray, Project Manager II

 

TITLE:                                                                                                                                                                         

title

Change Order: S-Line Extension Change Order 6 - Phase 1 Deductive Budget Adjustment (Kiewit West Infrastructure Co.)

end

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order 6 on Contract 24-03849 with Kiewit Infrastructure West Co. (Kiewit) to make a deductive contract adjustment in the amount of - $625,954 due to the completion of Phase 1 of the S-Line Extension project.                     

BACKGROUND:                                                                                                                                 

UTA has been working collaboratively with Salt Lake City to extend the S-Line Streetcar from the existing end of the line at Fairmont Station (1040 East) to the heart of the Sugarhouse Business District at Highland Drive.

UTA issued a RFP for a Progressive Design Build contractor to design and build the S-line Extension. On September 25, 2024, the UTA Board of Trustees approved contract 24-03849 with Kiewit for Phase 1 Pre-Construction Design Services on the S-Line Extension.

DISCUSSION:                                                                                                                                      

Kiewit has completed design services under Phase 1 of the contract and advanced the procurement of long lead items in previously approved change orders. There have been a variety of savings identified as the project has progressed.

CONTRACT SUMMARY:

 

Contractor Name

Kiewit West Infrastructure Co.

Contract Number

24-03849-06

Existing Contract Start/End Dates

09/25/24 - 01/31/26

New Contract Start/End Dates

N/A - N/A

Current Contract Value to Date

$9,039,323.11

Change/Task Order Amount

- $625,954.00

New Total Contract Value

$8,413,369.11

Procurement Method

RFP

Budget Authority

Approved 2026 Capital Budget

ALTERNATIVES                                                                                                                                  

This funding has not been spent. A change order is needed to un-obligate the funds so they can be used for construction. 

FISCAL IMPACT:

This change order will return $625,954.00 to the S-Line Extension (MSP259) budget.

                     Change Order 2 (Special Track Procurement) - Contingency not used: $178,205

                     Change Order 4 (Systems Early Procurement) - Overall reduction in price and contingency not used: $374,966

                     Change Order 5 (Additional Design Services) - Modification added $116,157 to the general agreement with the final invoice sent to UTA being $43,374 - a reduction of $72,783

Total Deductive Amount for Phase 1 - $625,954

ATTACHMENTS:                                                                                                                                

                     Change Order: S-Line Extension Change Order 6 - Phase 1 Deductive Budget Adjustment (Kiewit West Infrastructure Co.)