File #: 20-03349-24-004   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 5/22/2024 Final action: 5/22/2024
Title: Change Order: On-Call Infrastructure Maintenance Contract Task Order #24-004 - FrontRunner Gap Filler Installation (Stacy and Witbeck, Inc.)
Attachments: 1. Change order: On-Call Infrastructure Maintenance Ccontract Task Order #24-004 - Front Runner Gap Filler Install (Stacy and Witbeck, Inc.)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Service Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Design & Construction

 

Jacob WoudenRail, Infrastructure Project Manager

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Infrastructure Maintenance Contract Task Order #24-004 - FrontRunner Gap Filler Installation (Stacy and Witbeck, Inc.)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Task Order No. 24-004 and associated disbursements on the task ordering contract with Stacey and Witbeck, Inc.in the amount of $654,623.00 to install gap filler material on all FrontRunner platforms as part of the SGR program.                      

BACKGROUND:                                                                                                                                 

In October 2020, UTA released a request for procurement (RFP) for an on-call maintenance contractor focused specifically on infrastructure assets. Bids were received and evaluated, and Stacy and Witbeck, Inc. was selected as the winner based on overall scoring using the best value format. The UTA Board of Trustees approved the contract and authorized the Executive Director to execute the contract with Stacy and Witbeck Inc. on January 27, 2021.  This contract is for three years. A one-year extension was approved by the Board of Trustees in 2023 in preparation for re-procurement in 2024.

 

UTA’s rail infrastructure is at an age where yearly rehabilitations and replacements need to occur to maintain the infrastructure in a state of good repair. These projects typically address three concerns:
- Passenger ride quality
- Automobile cross-traffic ride quality
- Potential stray current issues

 

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval of Task Order 24-004 with Stacy Witbeck, Inc. to complete the install of gap filler material on all frontrunner station platform edges in the amount of $654,623.00.  The scope of this request includes all time, labor, and other items needed to install previously procured filler material. By installing this material, we will provide a safer transition to and from the train. This material will eliminate gaps between trains and the platform edge. This Task Order has been determined to be within the scope of the master Task Ordering Agreement. The Task Order pricing has been determined to be fair and reasonable based on both a UTA Independent Cost Estimate and performance of a Price Analysis.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stacy and Witbeck, Inc.

Contract Number:                          

20-03349-24-004

Base Contract Effective Dates:     

January 1, 2021 through December 31, 2023

Extended Contract Dates:            

January 1, 2024 through December 21, 2024

Existing Contract Value:                

$36,914,836

Amendment Amount:                   

$654,623

New/Total Contract Value:

$37,569,459

Procurement Method:                  

RFP best value modifications

Budget Authority:                            

Approved 2024 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

There are no alternatives. With installing this material, there will still be a gap between trains and platform edge, which could result in someone falling between and becoming trapped.

FISCAL IMPACT:                                                                                                                                

This project is included in the 2024 Capital budget