Title: Change Order: On-Call Systems Maintenance Contract Task Order #25-005 - Station Exempt Signal Removal (Rocky Mountain Systems Services)
Attachments: 1. Change Order: On-Call Systems Maintenance Contract Task Order #25-005 - Station Exempt Signal Removal (Rocky Mountain Systems Services)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Dave Hancock, Chief Officer of Capital Services

PRESENTER(S):

Jared Scarbrough, Director of Capital Design and Construction

 

Dean Hansen, Manager of Systems Engineering

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Systems Maintenance Contract Task Order #25-005 - Station Exempt Signal Removal (Rocky Mountain Systems Services)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Task Order 25-005 and associated disbursements with Rocky Mountain Systems Services in the amount of $343,272 to remove station exempt signals along the TRAX North/South mainline alignment.                     

BACKGROUND:                                                                                                                                 

UTA executed contract 24-03814VW with Rocky Mountain Systems Services (RMSS) for on-call systems maintenance. The term of this contract is for three years with two one-year term options. RMSS was selected based on best value procurement methodology. The UTA Board of Trustees approved the contract on June 12, 2024, and it was fully executed on June 14, 2024. The original contract value is not-to-exceed $40,000,000 at $8,000,000 per year.

Typical task orders under this contract include:

                     Support for rail and maintenance of way systems

                     Upgrades, repairs, analysis, and training of train control systems

                     Repair, maintenance, and training of overhead contact systems and traction power substations

DISCUSSION:                                                                                                                                      

Under Task Order 25-005, Rocky Mountain Systems Services will remove 16 station exempt signals along the TRAX North/South mainline alignment. These signals are no longer needed since UTA installed freight timers that adjust the crossing mode to provide warning time for freight trains. This task also includes updates to the train control logic to remove the XLOK software. Completion of this work is expected in September of 2025.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Rocky Mountain Systems Services

Contract Number:                          

24-03814-25-005

Base Contract Effective Dates:     

June 14, 2024 through July 1, 2027

Extended Contract Dates:            

N/A

Existing Contract Value:                

$4,425,261.55

Amendment Amount:                   

$343,272

New/Total Contract Value:

$4,768,533.55

Procurement Method:                  

RFP Best Value

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

Disapprove task order. This will leave signals in the system that are no longer used or needed. These signals may cause confusion to the light rail operators.

FISCAL IMPACT:                                                                                                                                

This task order allocates $343,272 of the 2025-2029 Capital Plan for the Train Control Rehabilitation and Replacement project (SGR403).

2025 Capital Budget: $8,000,000

Obligations:

     REQ 14533 - TO 25-003 General Engineering: $800,000

     REQ 14576 - TO 25-005 Station Exempt Signal Removal $343,272

2025 Capital Budget Remaining: $6,856,728

 

ATTACHMENTS:                                                                                                                                

Task Order