File #: 24-03849-07   
Type: Procurement Contract/Change Order Status: Agenda Ready
In control: Board of Trustees
On agenda: 4/8/2026 Final action:
Title: Change Order: S-Line Extension Change Order 7 - Phase 2 Construction Services (Kiewit West Infrastructure Co.)
Attachments: 1. Change Order: S-Line Extension Phase 2 Construction Services Change Order 7 – Extension Construction (Kiewit West Infrastructure Co.)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                

Board of Trustees

FROM:          

Jon Larsen, Chief Capital Services Officer

PRESENTER(S):

David Osborn, Acting Director of Capital Design and Construction

 

Ethan Ray, Project Manager II

 

TITLE:                                                                                                                                                                         

title

Change Order: S-Line Extension Change Order 7 - Phase 2 Construction Services (Kiewit West Infrastructure Co.)

end

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order 7 for Phase 2 Construction Services on Contract 24-03849 with Kiewit Infrastructure West Co (Kiewit).                     

BACKGROUND:                                                                                                                                 

UTA has been working collaboratively with Salt Lake City to extend the S-Line Streetcar from the existing end of the line at Fairmont Station (1040 East) to the heart of the Sugarhouse Business District at Highland Drive.

UTA issued a RFP for a Progressive Design Build contractor to design and build the S-line Extension. On September 25, 2024, the UTA Board of Trustees approved contract 24-03849 with Kiewit for Phase 1 Pre-Construction Design Services on the S-Line Extension.

DISCUSSION:                                                                                                                                      

Design services under Phase 1 of the contract were completed in January 2026 and, in accordance with Section 8 of the Construction and Design Services Agreement between Kiewit and UTA, UTA is authorized to issue an addendum authorizing Kiewit to construct an extension of the S-Line streetcar from Fairmont Station to a location directly east of Highland Drive. In lieu of issuing a contract addendum, UTA is issuing this Change Order to authorize Kiewit to enter into Phase 2 for Construction.

Note: UTA and Kiewit have agreed to set an effective date for Phase 2 as February 1, 2026, to cover the extended negotiation period required to finalize the Phase 2 Change Order and associated funding agreements.

CONTRACT SUMMARY:

 

Contractor Name

Kiewit West Infrastructure Co.

Contract Number

24-03849-07

Existing Contract Start/End Dates

9/26/2024 - 1/31/2026

New Contract Start/End Dates

2/01/2026 - 8/13/2027

Current Contract Value to Date

$8,413,369.11

Change/Task Order Amount

$23,866,561.00

New Total Contract Value

$32,279,930.11

Procurement Method

RFP

Budget Authority

Approved 2026 Capital Budget

ALTERNATIVES                                                                                                                                  

UTA could choose to rebid this contract. Doing so would cause delays and may result in additional costs.

FISCAL IMPACT:

The budget for this change order is included in UTA approved 2026 budget and planned 2027 budget.

                     2026 Change Order Total:                     $23,366,561.00                     Account # 40-3259.68000.8003

                     2027 Change Order Total:                     $500,000.00                                          Account # 40-3259.68000.8003

Total Change Order Amount: $23,866,561.00

Total Not-To-Exceed Contract Amount: $32,279,930.11