TO: |
Board of Trustees |
|
THROUGH: |
Jay Fox, Executive Director |
|
FROM: |
Dave Hancock, Chief Capital Services Officer |
|
PRESENTER(S): |
David Osborn, Project Manager III |
|
|
|
TITLE:

title
Contract: Cooperative Agreement for South Jordan Downtown 110000th South TRAX Platform (UDOT and South Jordan City)
end

AGENDA ITEM TYPE:
Non-Procurement Agreement

RECOMMENDATION:
Approve and authorize the Executive Director to execute a cooperative agreement with the Utah Department of Transportation (UDOT) and South Jordan City to transfer Transit Transportation Investment Funds (TTIF) and matching funds in the amount of $6 million to UTA for construction of a new TRAX platform in South Jordan.

BACKGROUND:
The original plan and agreements for the Mid-Jordan Trax line indicated that there would be an additional TRAX platform constructed in the South Jordan area to support population growth and development when it occurred.
New development is rapidly occurring in this area. South Jordan City approached UTA in 2023 to request a new station to support the ongoing growth in the area. South Jordan City has secured TTIF funding and the necessary match from the Utah State Legislature and Salt Lake County to fund the project.
The agreement is for a 2-year period. UTA will endeavor to have the platform ready for service prior to April 15, 2025.

DISCUSSION:
This agreement is to transfer the funding South Jordan has obtained for the project to UTA for the design and construction of the new platform.

CONTRACT SUMMARY:
|
Contractor Name: |
Utah Department of Transportation and South Jordan City |
|
Contract Number: |
24-00349 |
|
Base Contract Effective Dates: |
May 8, 2024-May 8, 2026 |
|
Extended Contract Dates: |
N/A |
|
Existing Contract Value: |
N/A |
|
Amendment Amount: |
N/A |
|
New/Total Contract Value: |
$6,000,000 |
|
Procurement Method: |
N/A |
|
Budget Authority: |
Approved 2024 Capital Budget |
|
|
|
ALTERNATIVES:
Do not accept the funding and do not construct the new platform.

FISCAL IMPACT:
Funding for this effort is included in project MSP 300 for 2024 and 2025. The plan includes $4,500,000 for 2024 and $1,500,000 for 2025, which is the TTIF and match funding this agreement describes.

ATTACHMENTS:
Agreement