File #: 22-128   
Type: Resolution Status: Passed
In control: Board of Trustees
On agenda: 3/23/2022 Final action: 3/23/2022
Title: R2022-03-07 - Resolution Authorizing Execution of Amendment Two to the Interlocal Cooperation Agreement with the Redevelopment Agency of Salt Lake City for the Cooperative Construction of a TRAX Station at 650 South Main Street
Attachments: 1. R2022-03-07_Authorizing Amendment 2 to ILA with RDA SLC for 650 S Trax Station_executed, 2. R2022-03-07_Authorizing Amendment 2 to ILA with RDA SLC for 650 S Trax Station_legal, 3. Presentation-R2022-03-07

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

David Hancock, Director of Capital Construction

 

David Osborn, Project Manager

 

TITLE:                                                                                                                                                                         

title

R2022-03-07 - Resolution Authorizing Execution of Amendment Two to the Interlocal Cooperation Agreement with the Redevelopment Agency of Salt Lake City for the Cooperative Construction of a TRAX Station at 650 South Main Street

end

 

AGENDA ITEM TYPE:                                                                                                                        

Resolution

RECOMMENDATION:                                                                                                                       

Approve Resolution R2022-03-07 authorizing Amendment Two for the Interlocal Cooperation Agreement (ILA) with Salt Lake City to extend the contract to June 30, 2022.                      

BACKGROUND:                                                                                                                                 

On December 16, 2020 the UTA Board of Trustees approved a resolution R2020-12-12 for the Interlocal Agreement/Cooperative Construction Agreement with Salt Lake City Redevelopment Agency (SLCRDA) for the construction of the 650 South Main Street TRAX Station.  A resolution R2021-07-01 for Amendment No. 1 was approved by the Board on July 14, 2021 with the initial construction bid and schedule. 

DISCUSSION:                                                                                                                                      

This Amendment No. 2 is to extend the milestone completion dates for the project.  Unanticipated supply chain issues have necessitated the need for additional time to complete the project.

Milestone completion dates are being extended as shows in the tables below:

Current Construction Milestone Dates Contained in Exhibit B

 

Construction*

Start Date

Completion Date

Mobilization

7/21/2021

7/22/2021

Construct Platform

7/22/2021

121/154/20212

Install Artwork

12/31/2021

121/1514/20212

Startup Testing

121/154/20221

12/14/20212

Punchlist

121/1514/20221

12/14/20212

 

 

 

Operation

 

 

Opening Day

 

No later than 23/2831/2022

 

New Construction Milestone Dates contained in updated Exhibit B as a result of Amendment No. 2:

Construction*

Start Date

Completion Date

Mobilization

7/28/2021

7/29/2021

Construct Platform

7/29/2021

6/30/2022

Install Artwork

3/31/2021

6/30/2022

Startup Testing

4/30/2022

6/30/2022

Punchlist

4/30/2022

6/30/2022

 

 

 

Operation

 

 

Opening Day

 

No later than 6/30/2022

 

ALTERNATIVES:                                                                                                                                    

If this amendment does not move forward, Utah Transit Authority is at risk of not completing the construction and opening the new platform within the timeframe of the agreement.

FISCAL IMPACT:                                                                                                                                

 The project construction is funded in the 2022 Capital Budget and this contract will cover that funding. There is no additional funding required for this Amendment No. 2.

ATTACHMENTS:                                                                                                                                

                     Resolution R2022-03-07