Legislation Details

File #: 22-035674VW   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 10/12/2022 Final action: 10/12/2022
Title: Contract: Task Ordering Agreement for TOD Station Area Planning Consultant Pool G (Economic & Planning Systems, Inc.)
Attachments: 1. Task Ordering Agreement for TOD Station Area Planning Consultant Pool G (Economic & Planning Systems)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Paul Drake, Director of Real Estate & TOD

PRESENTER(S):

Jordan Swain, TOC Project Manager

 

TITLE:                                                                                                                                                                         

title

Contract: Task Ordering Agreement for TOD Station Area Planning Consultant Pool G (Economic & Planning Systems, Inc.)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Authorize the Executive Director to execute the task ordering agreement and associated disbursements with Economic & Planning Systems (EPS) to add them to the Station Area Planning Pool of Consultants.                                           

BACKGROUND:                                                                                                                                 

UTA is providing technical assistance to cities that are completing station area planning work in response HB462 requirements.

DISCUSSION:                                                                                                                                      

In response to HB462, the TOC Department is setting up and maintaining a pool of pre-qualified consultants that may be solicited to complete particular tasks via task order. Said pool will increase UTA’s efficiency and ability to respond to the needs of our partner cities.  Economic & Planning Systems has been chosen to be part of Pool G to perform work in Market Analysis.  No work is authorized, nor funds obligated until a task order is issued under this contract. If the total cost of task orders issued under this agreement exceeds $200,000, additional Board approval will be required.

 

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Economic & Planning Systems, Inc. (EPS)

Contract Number:                          

22-035674

Base Contract Effective Dates:     

11/01/2022 to 11/01/2027

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$200,000 is the estimated cumulative cost.

Procurement Method:                  

RFQU (Qualification)

Budget Authority:                            

This project is included in the 2022 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

N/A

FISCAL IMPACT:                                                                                                                                

Station area plans will be funded through a combination of FTA grants, partner funds, and UTA capital funds.

ATTACHMENTS:                                                                                                                                

1.                     Task Ordering Agreement