Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 9/10/2025 Final action: 9/10/2025
Title: Contract: ECO Bus Lift Replacement - Mt. Ogden (Stertil-Koni USA, Inc.)
Attachments: 1. Contract: ECO Bus Lift Replacement – Mt. Ogden (Stertil-Koni USA, Inc.)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Andrés Colman, Chief Operations Officer

PRESENTER(S):

Kevin Anderson, Director of Maintenance Support

 

 

 

TITLE:                                                                                                                                                                         

title

Contract: ECO Bus Lift Replacement - Mt. Ogden (Stertil-Koni USA, Inc.)end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Purchase Order 17596, under State of Utah Contract PA4107, and associated disbursements in the amount of $305,916.42 with Stertil-Koni USA, Inc. for the purchase of a bus lift for the Mt. Ogden bus garage.                        

BACKGROUND:                                                                                                                                 

The current bus lift at Mt. Ogden was a prototype unit and has reached the end of its useful life and needs to be replaced. This unit is no longer supported by the manufacturer, is no longer maintainable, and is expected to fail its next scheduled inspection. UTA is utilizing the State of Utah contract for this procurement.

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval to procure an ECO Bus Lift from Stertil-Koni in the amount of $305,916.42.  The procurement includes the applicable federal clauses since a percentage of the funding may be reimbursed through a federal grant.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stertil-Koni USA, Inc.

Contract Number:                          

Utah State Contract: PA4170

Purchase Order: 17596

Base Contract Effective Dates:     

Utah State Contract: April 1, 2023 – March 31, 2028

Purchase Order: Effective after the last signature received - April 30, 2026

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$305,916.42

Procurement Method:                  

Utah State Contract PA 4107

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

There is no reasonable alternative, as not replacing the bus lift would eventually close the bay -negatively impacting bus service, and maintenance.

FISCAL IMPACT:                                                                                                                                

                     Funding for the new ECO Bus Lift for Mt. Ogden will come from the Capital budget 40-1652.65000.5008 FMA652 2025 Contract total: $5,000.00

                     2026 Contract total: $300,916.42