File #: 25-P00469   
Type: Resolution Status: Passed
In control: Board of Trustees
On agenda: 6/25/2025 Final action: 6/25/2025
Title: R2025-06-03 - Resolution Authorizing Execution of an Interlocal Cooperation Agreement with Salt Lake County for Davis-Salt Lake City Community Connector Project Funding
Attachments: 1. R2025-06-03 - Authorizing Execution of an Interlocal Coop Agreement with SLCo for Davis-SLC Community Connector - Legal

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Services Officer

PRESENTER(S):

Patti Garver, Manager of Environmental Compliance & Sustainability

 

 

 

TITLE:                                                                                                                                                                         

title

R2025-06-03 - Resolution Authorizing Execution of an Interlocal Cooperation Agreement with Salt Lake County for Davis-Salt Lake City Community Connector Project Funding

end

 

AGENDA ITEM TYPE:                                                                                                                        

Resolution

RECOMMENDATION:                                                                                                                       

Approve resolution R2025-06-03 authorizing the Executive Director to execute an Interlocal Cooperation Agreement (ILA) with Salt Lake County to provide UTA with $500,000 to be used for the Davis-Salt Lake City Community Connector project.                     

BACKGROUND:                                                                                                                                 

During the 2018 General Session, the Utah State Legislature enacted Senate Bill 136, which allowed for a one percent local option sales and use tax, which is used by Salt Lake County (the County) in its Regional Transportation Choice Fund (4th Quarter), which provides for on-going transportation funding in Salt Lake County (Transportation Funds).).

DISCUSSION:                                                                                                                                      

The Salt Lake County Council has appropriated Transportation Funds to further regional transportation by financing all or a portion of the costs of transportation projects throughout the County. Among these projects is the Davis-Salt Lake City Community Connector. Project Partners include UTA and Salt Lake County.

The aim of the Project is to establish a Bus Rapid Transit system utilizing existing roadways and without dedicated lanes to provide scheduled, public transit from the University of Utah Research Park in Salt Lake City to cities in Davis County including Bountiful, Centerville, and North Salt Lake and ending at the Farmington FrontRunner Station.


Salt Lake County, through this agreement, will reimburse UTA up to $500,000 for costs authorized under the Agreement.  UTA will provide a project status update to the County annually until all allocated funds have been disbursed.

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Salt Lake County

Contract Number:                          

25-P00469

Base Contract Effective Dates:     

June 25,2025 - June 30, 2028

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$500,000

Procurement Method:                  

ILA

Budget Authority:                            

2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

If this funding agreement is not executed, UTA would forego receiving county funds to aid in the implementation of the Davis-SLC Community Connector which aims to remove barriers to community connections and improve connections to mobility.

FISCAL IMPACT:                                                                                                                                

UTA’s 5-year capital plan includes $41,506,000 in MSP202 for Davis-SLC Community Connector. This funding from Salt Lake County will offset UTA project costs by $500,000.

ATTACHMENTS:                                                                                                                                

Resolution R2025-06-03, including the 4th Quarter ILA as an exhibit