TO: |
Board of Trustees |
|
THROUGH: |
Jay Fox, Executive Director |
|
FROM: |
Nichol Bourdeaux, Chief Planning and Engagement Officer |
|
PRESENTER(S): |
Jaron Robertson, Acting Planning Director |
|
|
|
TITLE:

title
Change Order: Microtransit Master Service Agreement Service Order No. 3 - UTA On Demand Southern Davis County (River North Transit LLC “Via”)
end

AGENDA ITEM TYPE:
Procurement Contract/Change Order

RECOMMENDATION:
Approve the UTA-Via Service Order No. 3 and authorize UTA’s Executive Director to execute the contract and associated disbursements with River North Transit LLC (Via) for the Southern Davis County UTA On-Demand microtransit service for the amount of $2,282,200.

BACKGROUND:
The UTA - Via Service Order No. 3 is the third service order under the UTA - Via Master Services Agreement (MSA) for On Demand Technologies and Innovative Services ( approved by the UTA Board of Trustees on August 25, 2021). The service order defines the parameters for operation of the Southern Davis County UTA On-Demand microtransit service. This service will be deployed during the August 2022 UTA change day. The Southern Davis County UTA On-Demand microtransit service will be UTA’s third microtransit deployment and is defined within UTA’s Five-Year Service Plan.

DISCUSSION:
Staff will discuss the change order and proposed UTA On-Demand microtransit service, which will include an overview of the following topics:
- Purpose: UTA Five-Year Service Plan and August 2022 changes
- Microtransit service overview including goals and objectives, service area, service parameters, operating day and hours, customer experience, fares and budget.

CONTRACT SUMMARY:
|
Contractor Name: |
River North Transit LLC (Via) |
|
Contract Number: |
20-03399-3 |
|
Base Contract Effective Dates: |
September 4, 2021 - 2026: Master Service Agreement |
|
Extended Contract Dates: |
August 8, 2022 - December 31, 2023 |
|
Existing Contract Value: |
$14,341,142 |
|
Amendment Amount: |
$2,282,200 |
|
New/Total Contract Value: |
$16,623,342 |
|
Procurement Method: |
Competitive Procurement (MSA) |
|
Budget Authority: |
2022 IMS Budget: $636,155 |
|
|
|
ALTERNATIVES:
The Southern Davis County UTA On-Demand microtransit service is a planned service as part of the agencies Five-Year Service Plan and August 2022 change day.

FISCAL IMPACT:
- 2022 planned expenses: $636,155
- 2023 planned expenses: $1,646,045
- Total Service Order No. 3 NTE: $2,282,200

ATTACHMENTS:
UTA - Via Service Order No. 3: Southern Davis County Deployment