Legislation Details

File #: 21-034961VW-3   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 8/10/2022 Final action: 8/10/2022
Title: Change Order: FrontRunner Forward Environmental Services Master Task Ordering Agreement, Task Order No. 3 - Advanced Conceptual Design for American Fork, Lehi, Woods Cross, Clearfield Strategic Double Track Projects (Parametrix Consult, Inc.)
Attachments: 1. FrontRunner Forward Environmental Services Master Task Ordering Agreement, (MTOA), Task Order No. 3 -

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

Dave Hancock, Director of Capital Development

 

Janelle Robertson, Project Manager

 

TITLE:                                                                                                                                                   

title

Change Order: FrontRunner Forward Environmental Services Master Task Ordering Agreement, Task Order No. 3 - Advanced Conceptual Design for American Fork, Lehi, Woods Cross, Clearfield Strategic Double Track Projects (Parametrix Consult, Inc.)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve award and authorize the Executive Director to execute the FrontRunner Forward Environmental Services master task ordering agreement Task Order No. 03 with Parametrix Consult, Inc., with its associated disbursements, in the amount of $1,519,521.

BACKGROUND:                                                                                                                                 

UTA identified nine strategic double track improvement projects to FrontRunner. UTA desires to advance projects through the environmental and preliminary design processes.

In an effort to advance FrontRunner Forward projects promptly, UTA selected a pool of qualified consultants through an RFQ process.  Parametrix Consult, Inc. was selected as part of the pool and on January 12, 2022 the UTA Board of Trustees approved a master task ordering agreement with Parametrix.  The pool of qualified environmental consultants allows UTA to advance into environmental study and conceptual design.

UTA desires to execute a third Task Order to the master task ordering agreement with Parametrix Consult, Inc. to provide advanced conceptual design services for several of the strategic double track projects.

 

 

DISCUSSION:                                                                                                                                      

Parametrix is currently under contract to prepare environmental study for American Fork, Lehi, Woods Cross, and Clearfield Strategic Double Track Projects. Through Task Order No. 3 Parametrix will prepare advanced conceptual design (25% design) for the segments to advance FrontRunner improvements.  Completing this work will assist UTA and UDOT in completing the environmental assessment, updating cost estimates, and preparing for a Federal Grant request.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Parametrix Consult., Inc.

Contract Number:                          

21-034961VW-3

Base Contract Effective Dates:     

Jan 27, 2022 - Jan 31, 2027

Extended Contract Dates:            

Task Order Term: July 12, 2022 - March 31, 2023

Existing Contract Value:                

$692,725 (Task Order #1)

 

$76,616.00 (Task Order #2)

 

TOTAL: $769,341.00

Amendment Amount:                   

$1,519,521 (Task Order #3)

New/Total Contract Value:

$2,288,862

Procurement Method:                  

Task Order Agreement

Budget Authority:                            

Capital project budget MSP 252

 

 

ALTERNATIVES:                                                                                                                                    

UTA could decide to not approve a task order with Parametrix Consult., Inc. This decision could delay the advancement of design work for the strategic double track projects identified by UTA.

FISCAL IMPACT:                                                                                                                                

The budget for task orders for environmental services pool consultant is included in this year’s capital budget.

ATTACHMENTS:                                                                                                                                

Task Order