TO: |
Board of Trustees |
|
THROUGH: |
Jay Fox, Executive Director |
|
FROM: |
Dave Hancock, Chief Capital Services Officer |
|
PRESENTER(S): |
David Osborn, Project Manager III |
|
|
|
TITLE:

title
Change Order: Depot District Clean Fuels Technology Center Contract Change Order No. 43 - Underground Power Unused Provisional Sum Credit (Big-D Construction)
end

AGENDA ITEM TYPE:
Procurement Contract/Change Order

RECOMMENDATION:
Approve and authorize the Executive Director to execute the deductive change order #43 with Big D construction in the amount of -$257,183.85.

BACKGROUND:
The phase 1 contract with Big D Construction to build the Depot District Clean Fuels Technology Center was executed in August of 2018, and a change order for phase 2 was approved by the Board of Trustees on June 19, 2019.
Provisional sums were included in the change order for the underground power service from 600 West along 200 South to the UTA property for contaminated soils, railroad insurance and permits, dewatering, utility test holes, utility adjustments due to underground conflicts, inclement weather, and Union Pacific railroad monitoring and construction observation. Use of these provisional sums for items with a difficult to determine cost or quantity reduces risk to both UTA and the contractor. The contract amount for these items was $465,000. The contractor was reimbursed for actual costs of $207,816.85.

DISCUSSION:
This deductive change order is to reduce the contract amount of the provisional sums to match the actual costs incurred by the contractor and paid by UTA.

CONTRACT SUMMARY:
|
Contractor Name: |
Big D Construction |
|
Contract Number: |
18-2741-43 |
|
Base Contract Effective Dates: |
August 24, 2018 (Phase 1 contract) June 24, 2019 (Phase 2 contract) |
|
Extended Contract Dates: |
January 31, 2024 |
|
Existing Contract Value: |
$78,061,22538 |
|
Amendment Amount: |
-$257,183.85 |
|
New/Total Contract Value: |
$77,804,041.53 |
|
Procurement Method: |
N/A |
|
Budget Authority: |
2024-2028 UTA Capital Plan |
|
|
|
ALTERNATIVES:
N/A

FISCAL IMPACT:
This project is included in the 2024 Capital Budget which is part of the approved 5-year Capital Plan. This change order reduces the overall contract amount.

ATTACHMENTS:
1) Big-D CO #43 Change Order