File #: 23-03811-26-011   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 5/13/2026 Final action: 5/13/2026
Title: Change Order: On-Call Infrastructure Maintenance Contract Task Order #26-011: 2100 South Grade Crossing Replacement (Stacy and Witbeck, Inc.)
Attachments: 1. Task Order: On-Call Infrastructure Maintenance Contract Task Order #26-011: 2100 South Grade Crossing Replacement (Stacy and Witbeck, Inc.)

TO:                

Board of Trustees

FROM:          

Jon Larsen, Chief Capital Services Officer

PRESENTER(S):

Dave Osborn, Acting Director of Capital Design and Construction

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Infrastructure Maintenance Contract Task Order #26-011: 2100 South Grade Crossing Replacement (Stacy and Witbeck, Inc.)

end

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Task Order 26-011 and associated disbursements on the On-Call Infrastructure Maintenance task ordering contract with Stacy and Witbeck, Inc. in the amount of $410,462 to replace the 2100 South Grade Crossing on the North/South TRAX line as part of the state of good repair transit asset management plan.                     

BACKGROUND:                                                                                                                                 

On April 17, 2024, the UTA Board of Trustees approved the contract and authorized the Executive Director to execute the master task ordering agreement (MTOA) with Stacy and Witbeck Inc. for on-call maintenance services focused specifically on infrastructure assets. 

The MTOA is contracted for a period of three years, plus two one-year options, with a total 5-year not-to-exceed amount of $45,000,000.

Tamping and regulating a rail line are essential maintenance activities that ensure the stability, safety, and smooth operation of a railway track. Tamping involves compacting and adjusting the ballast (the layer of crushed stones beneath and around the ties) to ensure the track is level and properly supported. Regulating involves redistributing and shaping the ballast to maintain the proper profile and ensure it is evenly distributed around the ties. Together, tamping and regulating maintain the integrity and geometry of the rail line, ensuring:

1.                     Smooth and safe train operations

2.                     Reduced long-term maintenance costs

3.                     Prolonged track life

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval of Task Order 26-011 with Stacy Witbeck, Inc. to complete the removal and replacement of the 2100 South Grade Crossing on the North/South TRAX  line in the amount of $410,462.

The scope of this request includes all time, labor, and other items needed to remove the old crossing panels and replace with new embedded crossing.  These are essential maintenance activities that ensure the stability, safety, and smooth operation of railway cars through the intersection as well as vehicles traveling across the crossing.

This task order is within the scope of the master task ordering agreement. The task order pricing has been determined to be fair and reasonable based on both a UTA independent cost estimate and performance of a price analysis.

CONTRACT SUMMARY:

 

Contractor Name

Stacy and Witbeck, Inc.

Contract Number

23-03811-26-011

Existing Contract Start/End Dates

April 30, 2024 - April 30, 2027

New Contract Start/End Dates

N/A - N/A

Current Contract Value to Date

$32,444,547.64

Change/Task Order Amount

$410,462.00

New Total Contract Value

$32,855,009.64

Procurement Method

RFP Best Value

Budget Authority

Approved 2026 Capital Budget

ALTERNATIVES                                                                                                                                  

Leave the crossing as is, resulting in rough track and grade crossing as well as adding to the TAM backlog.

FISCAL IMPACT:

The 2026-2030 approved Five Year Capital Plan includes $410,462 for this task order. This work will occur in 2026 under the Grade Crossing Program (SGR393). These costs will be offset by using federal formula grant funds.  These funds are part of UTA’s yearly apportionment. 

                     2026 Task Order Total: $410,462 (Account # 20-2502.55000.122403)

Total Master Task Ordering Agreement not-to-exceed $45,000,000

Total Master Task Ordering Agreement remaining balance: $12,144,990.36

The 2026 approved budget for SGR393 includes $2,000,000.00 for UTA’s Grade Crossing Replacement Projects.

Current remaining 2026 approved budget for SGR393: $466,696.50

ATTACHMENTS:                                                                                                                                

                     Task Order: On-Call Infrastructure Maintenance Contract Task Order #26-011: 2100 S Grade Crossing Replacement (Stacy and Witbeck, Inc.)