Skip to main content
Utah Transit Authority header
File #: 21-03502-04   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 4/12/2023 Final action: 4/12/2023
Title: Change Order: Final Design for Mid-Valley Connector - Change Order #04 (Jacobs Engineering)
Attachments: 1. Change Order-MidValley Connector CO#04 (Jacobs Engineering)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

David Hancock, Director of Capital Development

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Final Design for Mid-Valley Connector - Change Order #04 (Jacobs Engineering)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order 4 to the contract and associated disbursements with Jacobs Engineering in the amount of $871,826 for design work on the Mid-Valley Connector project.
                     

BACKGROUND:                                                                                                                                 

On December 15, 2021, the UTA Board approved the award of a sole source contract to Jacobs Engineering to finalize the design and prepare the Mid-Valley Connector Bus Rapid Transit (BRT) project for advertisement. Through a Taylorsville City contract, Jacobs had completed the environmental assessment and preliminary design for the project.  Since Jacobs was familiar with the project, the stakeholders and UTA felt that they should perform the final design on the project.  The UTA Sole Source Committee approved the sole source award to Jacobs on the basis of substantial duplication of costs. The contract time was extended in early 2023 to incorporate anticipated consultant needs during the construction phase of the project.

 

DISCUSSION:                                                                                                                                      

This change order includes additional scope modifications for future efforts to complete the final plans and specifications, and management support through the contractor bidding process. This change order also includes supplemental scope items that have been requested by stakeholders since the latest design package was released.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Jacobs Engineering Group, Inc.

Contract Number:                          

21-03502-04

Base Contract Effective Dates:     

December 17, 2021 - December 31,2022

Extended Contract Dates:            

January 1, 2023 - December 31, 2026

Existing Contract Value:                

$3,000,027

Amendment Amount:                   

$871,826

New/Total Contract Value:

$3,871,853

Procurement Method:                  

Sole Source

Budget Authority:                            

2023-2027 Capital Plan

 

 

ALTERNATIVES:                                                                                                                                    

If this change order is not executed, UTA would need to procure another consultant to finalize the project design and prepare the construction bid documents.

FISCAL IMPACT:                                                                                                                                

The 2023-2027 Capital Plan called for State and Federal Funds on this project.  UTA received $22.8M from the State of Utah through UDOT in March 2023. This agreement was approved by the board on 12/21/22. Federal funds are anticipated through the Capital Investment Grant program.

ATTACHMENTS:                                                                                                                                

1)                     Jacobs Change Order #4