Legislation Details

File #: 23-03791   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 10/23/2024 Final action: 10/23/2024
Title: Contract: Twenty New Light Rail Vehicles (Stadler US)
Attachments: 1. Contract: Twenty New Light Rail Vehicles (Stadler)_redacted

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Service Officer

PRESENTER(S):

Kyle Stockley, Manager of Capital Vehicles

 

 

 

TITLE:                                                                                                                                                                         

title

Contract: Twenty New Light Rail Vehicles (Stadler US)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize Executive Director to execute a procurement contract and associated disbursements with Stadler US in the amount of $129,300,194 for the base order of 20 light rail vehicles.  Exercise of any additional options will require future board approval.                     

BACKGROUND:                                                                                                                                 

UTA’s SD100 and SD160 light rail vehicles are nearing the end of their useful life. Because of this, UTA applied for a Federal Transit Administration (FTA) rail vehicle replacement grant. In May of 2023, the FTA selected UTA for a $60,000,000 light rail vehicle replacement grant.

 

UTA conducted industry workshops to collaborate with potential vendors. In December 2023, UTA released an RFP requesting proposals to procure new light rail vehicles.

 

DISCUSSION:                                                                                                                                      

UTA staff is requesting approval of a light rail vehicle procurement contract with Stadler US, totaling $129,300,194. This request involves the procurement of the base order of 20 low floor light rail vehicles to replace 20 SD100 high floor light rail vehicles.

 

The light rail vehicles are part of the 2024-2028 capital plan.

 

UTA had included 60 options for additional vehicles for future procurements.

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stadler US

Contract Number:                          

23-03791

Base Contract Effective Dates:     

10/2024 thru 10/2031

Extended Contract Dates:            

N/A

Existing Contract Value:                

$0.00

Amendment Amount:                   

N/A

New/Total Contract Value:

$129,300,194

Procurement Method:                  

RFP - Request for Proposal

Budget Authority:                            

Approved 2024 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

Not replace the aging high floor light rail vehicles.

FISCAL IMPACT:                                                                                                                                

This light rail vehicle procurement is included UTA’s current 2024-2028 Five Year Capital Plan. The 2024-2028 Capital Plan has the following total yearly amounts in project REV238 with a total of $227,300,000 in it over the current five-year period:

                     2024: Total approved budget is $500,000. Planned spend is $300,000.

                     2025: Total approved plan amount is $36,000,000. Total planned spend amount is $34,400,000

                     2026: Total approved plan amount is $36,000,000. Total planned spend amount is $27,200,000

                     2027: Total approved plan amount is $37,900,000. Total planned spend amount is $36,900,000

                     2028: Total approved plan amount is $120,000,000. Total planned spend amount is $30,500,194.

Total Budget amount for the planned spend: $129,300,194

 

ATTACHMENTS:                                                                                                                                

1)                     Contract