Skip to main content
Utah Transit Authority header
File #: 25-P00472   
Type: Non-Procurement Agreement Status: Passed
In control: Board of Trustees
On agenda: 6/25/2025 Final action: 6/25/2025
Title: Revenue Contract: FrontRunner South Extension Memorandum of Funding Agreement (Mountainland Association of Governments)
Attachments: 1. Revenue Contract: FrontRunner South Extension Memorandum of Funding Agreement (Mountainland Association of Governments)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Services Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Design & Construction

 

 

 

TITLE:                                                                                                                                                                         

title

Revenue Contract: FrontRunner South Extension Memorandum of Funding Agreement (Mountainland Association of Governments)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Non-Procurement Agreement

RECOMMENDATION:                                                                                                                       

Approve and authorize UTA’s Executive Director to execute the FrontRunner South Extension Memorandum of Funding Agreement with the Mountainland Association of Governments.                     

BACKGROUND:                                                                                                                                 

UTA, in partnership with Provo, Springville, Mapleton, Spanish Fork, Salem, Payson, Santaquin, Mountainland Association of Governments (MAG), and Utah Department of Transportation (UDOT) completed the South Valley Transit Study in 2022. This effort identified the locally preferred option for the FrontRunner South Extension.

The current phase of the project includes environmental review under the National Environmental Policy Act (NEPA) and preliminary design for the proposed commuter rail extension. UTA contracted AECOM Technical Services Inc. in March 2023 to perform the environmental and engineering work.

DISCUSSION:                                                                                                                                      

MAG has agreed to reimburse UTA $1,884,600 for expenses incurred during the environmental assessment and preliminary engineering phases of the project. This funding is part of a broader initiative supported by the Utah State Legislature, which allocated $5,000,000 in one-time funds under 2022 H.B. 3, Item 371, to support planning and environmental efforts for the extension. As part of the agreement, UTA will provide a required $135,400 local match from the legislative funds.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Mountainland Association of Governments

Contract Number:                          

25-P00472

Base Contract Effective Dates:     

7/25/2025-12/15/2025

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$1,884,600 revenue

Procurement Method:                  

Non-Procurement Agreement

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

No alternative. If UTA does not approve this agreement, $1,884,600 in revenue will be lost for the FrontRunner South Extension project.

FISCAL IMPACT:                                                                                                                                

This project provides $1,884,600 of revenue. The funds transferred by this Agreement are an essential funding source for the project.

Capital Project MSP264 has an approved 2025 Capital Budget of $3,050,000.

ATTACHMENTS:                                                                                                                                

                     25-P00472 FrontRunner South Extension Memorandum of Funding Agreement