File #: 20-03349-93   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 4/12/2023 Final action: 4/12/2023
Title: Change Order: On-Call Infrastructure Maintenance Contract Task Order #23-93 - 5300 S. & 5400 S. Turnout Construction (Stacy and Witbeck, Inc)
Attachments: 1. Change Order-On-Call Infrastructure Task Order 23-93 (Stacy & Witbeck)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Construction

 

Kyle Stockley, Rail Infrastructure Project Manager

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Infrastructure Maintenance Contract Task Order #23-93 - 5300 S. & 5400 S. Turnout Construction (Stacy and Witbeck, Inc)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve task order #23-93 to the on-call maintenance contract with Stacy and Witbeck in the amount of $948,100 and authorize the Executive Director to execute the task order and associated disbursements for state of good repair work on the North/South TRAX line.                        

BACKGROUND:                                                                                                                                 

After approval by the board of trustees on January 27, 2021, UTA executed an on-call Infrastructure Contract with Stacy and Witbeck for the years 2021-2023 with a possibility to go two additional years at UTA’s discretion.  The primary purpose of the on-call contract is to maintain UTA’s infrastructure assets in a state of good repair.

 

The existing turnouts at 5300 south and 5400 south on the North/South TRAX line are part of the State of Good Repair program.  

DISCUSSION:                                                                                                                                      

If approved, this request is anticipated not to exceed $948,100 and will facilitate removal and replacement of the existing turnouts at 5300 South and 5400 South on the North/South TRAX line. There are 2 right hand #10 turnouts, and 1 left hand #10 turnout located at 5300 South. At 5400 South, 2 left hand #10 turnouts will be replaced.  Also included in this proposal is the purchase and installation of a new split point derail to be installed on concrete ties on the Murray Central siding. This work is to be performed in conjunction with a planned and detailed shutdown with RMSS working to upgrade signals and systems in this location at the same time.  A 25-day continuous shutdown is anticipated for this project. 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stacy and Witbeck Inc.

Contract Number:                          

20-03349-93

Base Contract Effective Dates:     

January 1, 2021 through December 31, 2023

Extended Contract Dates:            

N/A

Existing Contract Value:                

$23,829,801

Amendment Amount:                   

$948,100

New/Total Contract Value:

$24,777,901

Procurement Method:                  

RFP best value modification/on-call contract

Budget Authority:                            

2023-2027 Capital Plan

 

 

ALTERNATIVES:                                                                                                                                    

Due to the complexity of rail replacement work, starting a new procurement would delay the project 18 months due to the selection process and ordering materials. If 5300 S. & 5400 S. Turnouts are not replaced, the rail, switches, and turnout track will continue to deteriorate and cause service interruptions.  If delayed long enough, the rail would be out of a state of good repair and could become a severe safety issue. Due to the lead time of the materials needed for replacement, an unplanned replacement could impact service for over a year.  The location of the 5300 S. & 5400 S. Turnouts is on the TRAX Blue line which would significantly delay service if not replaced.  This is a key strategic alignment area for our operation team.

FISCAL IMPACT:                                                                                                                                

This budget is included in the 2023 Capital Program.

ATTACHMENTS:                                                                                                                                

1)                     Contract task order #93