Skip to main content
Utah Transit Authority header
File #: 23-036852-01   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 6/26/2024 Final action: 6/26/2024
Title: Change Order: Master Task Ordering Agreement for Bus System Enhancement Design Services Consultant Pools A, B, C - Change Order No. 1 - Exercise Option Years 1 and 2 (Focus Engineering and Surveying, LLC)
Attachments: 1. Change Order: Master Task Ordering Agreement for Bus System Enhancement Design Services Consultant Pools A, B, C - Change Order No. 1 - Exercise of Option Years 1 and 2 (Focus Engineering and Surveying, LLC)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Dave Hancock, Chief Capital Services Officer

PRESENTER(S):

Jared Scarbrough, Director of Capital Design & Construction

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Master Task Ordering Agreement for Bus System Enhancement Design Services Consultant Pools A, B, C - Change Order No. 1 - Exercise Option Years 1 and 2 (Focus Engineering and Surveying, LLC)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order #1 to the Master Task Ordering Agreement, and associated disbursements, with Focus Engineering & Surveying, LLC to exercise option years one and two  with a not-to-exceed value of $550,000 per year, $1,100,000 over the two option years recommended.                      

BACKGROUND:                                                                                                                                 

On June 14, 2023 the Board of Trustees approved contracting with a pool of pre-qualified consultants that may be solicited to complete tasks via task orders to increase UTA’s efficiency to deliver system enhancement projects yearly and utilize the programmed budget.  Local funding has been allocated yearly for Bus Stops, End of Line Facilities, and Operator Restrooms - Design Pools A, B, and C respectively to develop an ongoing yearly program of projects for bus system improvements.  Since requirements and budget are determined on an annual basis, these contracts were created for one year periods with 4 additional one-year options to be exercised each year contingent on the availability of funds. Board approval will be obtained prior to the exercise of each option year provided its value exceeds $200,000.

DISCUSSION:                                                                                                                                      

This request is to approve option years one and two.  If approved, Focus Engineering & Surveying, LLC. is qualified for design pools A, B, and C:

Pool A-Bus Stops: $300,000 for each option year per yearPool B-End of Line (EOL) Facilities: $100,000 for each option year per year

Pool C-Operator Restrooms: $150,000 for each option year per year

No work is authorized, nor funds obligated until a task order is issued under this contract. Individual task orders totaling $200,000 or more will be brought to the board for approval. If the cost of all task orders issued under this agreement exceeds $1,600,000 additional board approval will be required. Board approval will be obtained prior to the exercise of subsequent options years provided their value exceeds $200,000.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Focus Engineering & Surveying, LLC

Contract Number:                          

23-036852-01

Base Contract Effective Dates:     

June 20, 2023 - June 19, 2024

Extended Contract Dates:            

Option Year 1: June 20, 2024 - June 19, 2025 Option Year 2: June 20, 2025 - June 19, 2026

Existing Contract Value:                

$500,000

Amendment Amount:                   

$1,100,000.00

New/Total Contract Value:

$1,600,000.00

Procurement Method:                  

RFQu (Qualification)

Budget Authority:                            

Approved 2024 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

By not developing and maintaining a pool of consultants for design services, UTA is compromised in its ability to deliver system enhancement projects quickly. The alternative to executing contracts for design services in each pool category would require three RFQu’s for design services for every project or every year and create additional work while possibly impacting completion dates. The current approach streamlines the process, allows for more efficient delivery, and helps ensure the project gets completed on time.

FISCAL IMPACT:                                                                                                                                

Fiscal impact is a function of the total amount actually contracted via task order(s) under this Master Task Order Agreement.  Technically, this is an authorization to contract but not an actual commitment of funds.

ATTACHMENTS:                                                                                                                                

1.                     MTOA for Bus System Enhancement Change Order No. 1 (Focus Engineering)