TO: |
Board of Trustees |
|
THROUGH: |
Jay Fox, Executive Director |
|
FROM: |
Mary DeLoretto, Chief Capital Service Officer |
|
PRESENTER(S): |
Dean Hansen, Systems Engineering Manager |
|
|
|
TITLE:

title
Change Order: Traction Power Substations (TPSS) Rehabilitation Change Order #012 - New HVAC Systems (C3M Power Systems, LLC)
end

AGENDA ITEM TYPE:
Procurement Contract/Change Order

RECOMMENDATION:
Approve Change Order #012 to the TPSS Rehabilitation Contract with C3M Power Systems, LLC and authorize Executive Director to execute the change order and associated disbursements for new HVAC systems in the amount of $1,651,646.

BACKGROUND:
UTA has an existing contact with C3M Power Systems (C3M) to design and rehabilitate its Traction Power Substations (TPSS). This contract was approved by the Board of Trustees on June 23, 2021 and awarded to C3M on June 24, 2021. The substantial completion date for this contract is April 11, 2025.
As part of the base scope of work, C3M performed an evaluation of the nineteen (19) TPSS units listed in the contract. In this evaluation, the contractor discovered that the HVAC systems at eighteen (18) sites do not meet the design operating temperature range for the traction electrification system. The existing HVAC units often overheat and must be repaired. Increasing the cooling capacity will reduce maintenance costs and keep essential components cool enough to meet or exceed their intended life span.

DISCUSSION:
For this change order, C3M will install two 5-ton HVAC/heat pump systems at 15 TPSS locations and three 5-ton HVAC/heat pump systems at 3 TPSS locations. At the three 5-ton locations, the TPSS Auxiliary Transformers will be upgraded to 45kVA rating to accommodate increased power.

CONTRACT SUMMARY:
|
Contractor Name: |
C3M Power Systems, LLC |
|
Contract Number: |
20-03378-012 |
|
Base Contract Effective Dates: |
June 24, 2021 - April 11, 2025 |
|
Extended Contract Dates: |
N/A |
|
Existing Contract Value: |
$44,348,228 |
|
Amendment Amount: |
$1,651,646 |
|
New/Total Contract Value: |
$45,999,874 |
|
Procurement Method: |
RFP best value modification |
|
Budget Authority: |
2023-2027 Capital Plan |
|
|
|
ALTERNATIVES:
Leave the existing HVAC systems and run the risk of overheating causing equipment failure.

FISCAL IMPACT:
This budget is included in the 2023-2027 Capital Plan.

ATTACHMENTS:
Change Order