Skip to main content
Utah Transit Authority header
File #: 24-03880   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 3/12/2025 Final action: 3/12/2025
Title: Contract: Jordan River Rail Service Center - Truck Shop Wheel Press (MAE-Eitel, Inc.)
Attachments: 1. Contract: Jordan River Rail Service Center Truck Shop Wheel Press (MAE-Eithel, Inc.)

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Service Officer

PRESENTER(S):

Kyle Stockley, Manager of Capital Vehicles

 

 

 

TITLE:                                                                                                                                                                         

title

Contract: Jordan River Rail Service Center - Truck Shop Wheel Press (MAE-Eitel, Inc.)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute contract #24-03880 and associated disbursements with MAE-Eitel, Inc. in the amount of $946,761.48 to design, build, and commission a new wheel press for the Jordan River Rail Service Center.                      

BACKGROUND:                                                                                                                                 

With the growing and aging fleet of rail vehicles, rail vehicle overhaul services require a new wheel press machine to increase in-house capabilities for overhaul work.

In October 2024, UTA released a request for procurement (RFP) for a new wheel press for the Jordan River Rail Service Center truck shop. Bids were received and evaluated, and MAE-Eitel, Inc. was selected. 

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval of the contract with MAE-Eitel, Inc. to design, manufacture, test, deliver, install, and commission a RADS 2-250 wheelset assembly press machine capable of performing all pressing activities required to maintain, repair, and overhaul UTA’s rail vehicles.

 

The wheel press machine shall, at minimum, be capable of performing the following:

                     S70 Light Rail Vehicle Mounting and Dismounting Operations

                     SD-160 Light Rail Vehicle Mounting and Dismounting Operations

                     SD-100 Light Rail Vehicle Mounting and Dismounting Operations

                     Future UTA Light Rail and Frontrunner Vehicles

                     MP36PH-3C Locomotives

                     Bombardier Bi-Level Coaches and Cabs

                     Opposing Force Test for all applicable press applications

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

MAE-Eitel, Inc.

Contract Number:                          

24-03880

Base Contract Effective Dates:     

March 12, 2025 - March 31, 2026

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Contract Value:

$946,761.48

Procurement Method:                  

RFP - Best Value

Budget Authority:                            

Approved 2025 Capital Budget

 

 

ALTERNATIVES:                                                                                                                                    

UTA could forgo the purchase of the new wheel press for the Jordan River Rail Service Center truck shop. Doing so would hamper UTA's ability to service its rail fleet and increase dependency on outside vendors for overhaul services.

FISCAL IMPACT:                                                                                                                                

The expected spend for this request is $946,761.48. The approved 2025 Capital Budget includes $10,200,000 for UTA’s SGR040 Light Rail Vehicle Rehabilitation project.

                     Approved 2025 Budget Total: $10,200,000

- After current encumbrances, including this contract, budget availability is $7.0 million.

                     2026 Plan: $11,342,000

                     2027 Plan: $8,919,000

                     2028 Plan: $6,801,000

                     2029 Plan: $3,661,000

 

ATTACHMENTS:                                                                                                                                

                     Contract: Jordan River Rail Service Center Truck Shop Wheel Press (MAE-Eithel, Inc.)