File #: 20-03349-24-010   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 3/13/2024 Final action: 3/13/2024
Title: Change Order: On-Call Infrastructure Maintenance Contract Task Order #24-010 - Grade Crossing Other Track Materials Procurement (Stacy and Witbeck, Inc.)
Attachments: 1. Change order: On-Call Infrastructure Maintenance Contract Task Order #24-010 - Grade Crossing OTM Procurement (Stacy and Witbeck, Inc.)
Related files: 20-03349VW

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

David Hancock, Chief Capital Service Officer

PRESENTER(S):

Jacob Wouden, Project Manager

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Infrastructure Maintenance Contract Task Order #24-010 - Grade Crossing Other Track Materials  Procurement (Stacy and Witbeck, Inc.)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize Executive Director to execute Task Order No. 24-010, and associated disbursements,on the  task ordering contact with Stacey and Witbeck in the amount of $636,274.00 to procure other tack material for planned 2024 SGR work.                      

BACKGROUND:                                                                                                                                 

In October 2020, UTA released a request for procurement (RFP) for an on-call maintenance contractor focused specifically on infrastructure assets. Bids were received and evaluated, and Stacy and Witbeck, Inc. was selected as the winner based on overall scoring using the best value format. The UTA Board of Trustees approved the contract and authorized the Executive Director to execute the contract with Stacy and Witbeck Inc. on January 27, 2021.  This contract is for three years. A one-year extension was approved in 2023 in preparation for re-procurement in 2024.

 

UTA’s rail infrastructure is at an age where yearly rehabilitations and replacements need to occur to maintain the infrastructure in a state of good repair. These projects typically address three concerns:
- Passenger ride quality
- Automobile cross-traffic ride quality
- Potential stray current issues

 

DISCUSSION:                                                                                                                                      

UTA Staff is requesting approval of Task Order 24-010 with Stacy Witbeck, Inc. to complete the procurement of necessary track material for use in SGR crossing replacement in the amount of $636,274.00.  The scope of this request includes procurements of the required track materials (boot, steel ties, Magnum panels, 115# premium rail, and rebar) required to construct the embedded grade crossings located throughout the TRAX system, as well as panelized crossings on FrontRunner

 

The Task Orders have been determined to be within the scope of the master Task Ordering Agreement. The Task Order pricing has been determined to be fair and reasonable based on both a UTA Independent Cost Estimate and performance of a Price Analysis.

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stacy and Witbeck, Inc.

Contract Number:                          

20-03349-24-010

Base Contract Effective Dates:     

January 1, 2021 through December 31, 2023

Extended Contract Dates:            

January 1, 2024 thought December 21, 2024

Existing Contract Value:                

$35,424,797

Amendment Amount:                   

$636,274

New/Total Contract Value:

$36,061,071

Procurement Method:                  

RFP best value modification

Budget Authority:                            

2024 Capital Budget, 2024-2028 Capital Plan

 

 

ALTERNATIVES:                                                                                                                                    

Without these materials we would not be able to complete required grade crossings as part of the State of Good Repair program. Without replacement of worn track components, we face possible components fatigue which may result in derailment and service interruptions to the system.

FISCAL IMPACT:                                                                                                                                

The Budget for this task order is included in the 2024-2028 Approved Capital Plan.