File #: 21-P00135   
Type: Non-Procurement Agreement Status: Passed
In control: Board of Trustees
On agenda: 11/10/2021 Final action: 11/10/2021
Title: Contract: Pass Through Funding Agreement - Depot District 2022 Funding (Utah Department of Transportation)
Attachments: 1. UTA Pass Through Funds 500k13Sept21 UTA Edits

TO:                

Board of Trustees

THROUGH:  

Mary DeLoretto, Interim Executive Director

FROM:          

William Greene, Chief Financial Officer

PRESENTER(S):

William Greene, Chief Financial Officer

 

 

 

TITLE:                                                                                                                                                                         

title

Contract: Pass Through Funding Agreement - Depot District 2022 Funding (Utah Department of Transportation)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Non-Procurement Agreement

RECOMMENDATION:                                                                                                                       

Approve the Agreement to pass through $500,000 from UDOT to fund the Depot District Project at UTA

BACKGROUND:                                                                                                                                 

In Senate Bill 3, Item 169, the 2021 Utah State Legislature allocated a one-time total of $500,000 from the state’s General Fund to support construction of UTA’s Depot District project.

Utah Code Section 63J-1-220(2) mandates that UDOT may not provide UTA with state pass through funding unless an agreement is executed. 

DISCUSSION:                                                                                                                                      

The attached agreement (Exhibit A) details the terms of the agreement including the objective, payment schedule, key activities, budget and deliverables and roles of the parties to the agreement.

Upon execution of the agreement, UDOT commits to make four (4) equal payments to UTA on a quarterly basis.

 

 

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Utah Department of Transportation

Contract Number:                          

21-P00135

Base Contract Effective Dates:     

November 10, 2021 - June 30, 2022

Extended Contract Dates:            

N/A

Existing Contract Value:                

N/A

Amendment Amount:                   

N/A

New/Total Amount Contract Value:

$500,000

Procurement Method:                  

Pass Through Funds Agreement

Funding Sources:                            

State General Fund

 

 

ALTERNATIVES:                                                                                                                                    

Not accept the funds from the State.

FISCAL IMPACT:                                                                                                                                

These funds support the completion of the Depot District Project.

ATTACHMENTS:                                                                                                                                

Contract