Legislation Details

File #: 18-2741TP-31   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 10/26/2022 Final action: 10/26/2022
Title: Change Order: Depot District Clean Fuels Technology Center Change Order No. 31 - Phase 6 Onsite Underground Power Conduits and Vaults (Big-D Construction)
Attachments: 1. Big-D CO #31 GMP-6 - MSP102 Legal and Contractor signed

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

Dave Osborn, Project Manager III

 

 

 

TITLE:                                                                                                                                                                         

title

Change Order: Depot District Clean Fuels Technology Center Change Order No. 31 - Phase 6 Onsite Underground Power Conduits and Vaults (Big-D Construction)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve and authorize the Executive Director to execute Change Order No. 31 and associated disbursements with Big-D Construction in the amount of $2,604,560.                      

BACKGROUND:                                                                                                                                 

In June 2018, UTA released a request for procurement (RFP) for the construction of the Depot District Clean Fuels Technology Center. This facility will replace the existing aging and undersized Central bus facility and will house up to 150 alternative and standard fuel buses with the ability to expand to 250 buses in the future.  This contract first came to the board for approval of a change order for phase 2/GMP 1 on June 19, 2019. Rocky Mountain Power requires UTA to install underground conduit and vaults so they can provide wiring and equipment to provide the necessary power for the new facility.

DISCUSSION:                                                                                                                                      

This change order is to provide underground conduit and vaults from the parking lot out to 200 South and along 200 South to 600 West. Big-D Construction obtained pricing from three separate, qualified subcontractors. They are proposing to use the subcontractor that proposed the lowest cost.

A Direction or Authorization to Proceed (DAP) has been issued in the amount of $199,000 to order the precast concrete vaults and other materials which can take several weeks to deliver to the site. The DAP will also allow them to perform utility test holes to verify the locations of other underground facilities in the area and start obtaining the necessary permits for the work.  This change order also includes a contract time extension from March 10, 2023 to May 12, 2023.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Big-D Construction

Contract Number:                          

18-2741TP-31

Base Contract Effective Dates:     

August 24, 2018 (Phase 1 Contract) June 24, 2019 (Phase 2 Contract)

Extended Contract Dates:            

May 12, 2023

Existing Contract Value:                

$74,056,450

Amendment Amount:                   

$2,604,560

New/Total Contract Value:

$76,661,010

Procurement Method:                  

n/a

Budget Authority:                            

UTA Capital Budget, MSP102 for the Depot District

 

 

ALTERNATIVES:                                                                                                                                    

If this change order is not approved, Rocky Mountain Power will not be able to provide sufficient power for the new facility.

FISCAL IMPACT:                                                                                                                                

This project is included in the 5-Year Capital Plan. This change order adds $2,604,560 to the total Depot District project.  Sufficient funds remain in the project budget to cover the cost of this change order.