Utah Transit Authority header
File #: 25-139   
Type: Technical Budget Adjustment Status: Agenda Ready
In control: Board of Trustees
On agenda: 4/9/2025 Final action:
Title: TBA2025-04-01 - Technical Budget Adjustment - 2025 Capital Program
Attachments: 1. TBA2025-04-01_Exhibit
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Viola Miller, Chief Financial Officer

PRESENTER(S):

Daniel Hofer, Director- Capital Programming and Support

 

Greg Andrews, Senior Capital Budget Analyst

 

TITLE:                                                                                                                                                                         

title

TBA2025-04-01 - Technical Budget Adjustment - 2025 Capital Program

end

 

AGENDA ITEM TYPE:                                                                                                                        

Other Approval

RECOMMENDATION:                                                                                                                       

Approve TBA2025-04-01 to authorize transfer of $26,073,000 between various projects within the 2025 Capital Budget as presented.                     

BACKGROUND:                                                                                                                                 

Board Policy 2.3 Budget allows the Board of Trustees to amend or supplement the Authority’s budget at any time after its adoption. The Board may do this through a Technical Budget Adjustment (TBA) when the request does not increase budget authority, or through a Budget Amendment, after consultation with the Local Advisory Council, when an increase in the annual appropriation authority is requested.

DISCUSSION:                                                                                                                                      

This Technical Budget Adjustment will transfer a total of $26,073,000 between 88 projects, including the Capital Contingency (MSP999), within UTA’s 2025 capital program to aid in project delivery this year.  This request, if approved by the Board, will affect the current budget total of 87 different capital program projects and shift funds to the Capital Contingency.

This adjustment aims to redirect funds to aid in delivery of work that was not able to be completed in 2024. These adjustments should better align these projects to deliver remaining 2024 work as well as 2025 planned work. 

The attached exhibit provides detail for all projects included in this budged adjustment.

A summary of the benefits and reasons for the budget adjustments are provided below. 

The main benefit UTA anticipates to receive from the proposed Technical Budget Adjustment include:

                     Aligning budgets with remaining obligations and anticipated expenditure amounts for the projects thru the end of 2025 including unfinished 2024 work.

 

The reasoning and guidelines for the Technical Budget Adjustment are as follows:

Request:

​Absorb approximately $26.1 million in carryforward/early requests within a $330.2 million budget in April Technical Budget Adjustments

Approach:

                     ​Projects not hitting an 85% spend threshold for 2024 were subject to a 10% reduction in 2025

                     ​Surplus funding sources placed in Capital Contingency line

                     ​Funding sources were cut proportionally on projects receiving funding reductions

                     ​Funds were redistributed based on need and known funding gaps

                     ​More significant cuts as needed to free up appropriate amounts of correct funding sources

Obligations and Balancing:

                     ​Priority was to address current contractual obligations as needed by Project Managers

                     ​Ensured all offices had a stake in the process, balancing this with their obligations

Summary of Results:

​The tables below show projects that have been impacted by this Technical Budget Adjustment and how much they will be adjusted.  The first summary table is the impact by chief office.  The last two tables are the top projects impacted by the adjustment in terms of overall dollar change.

 

Summary by Chief

Chief Office

2025 Adopted Budget

April 9th TBA

2025 Adjusted Budget

Capital Services

$275,890,000

$(7,763,000)

$268,127,000

Enterprise Strategy

15,872,00

2,783,000

18,655,000

Executive Director (Safety)

2,078,000

(318,000)

1,760,000

Finance

21,148,000

5,488,000

26,636,000

Operations

9,705,000

513,000

10,218,000

People

2,145,000

325,000

2,470,000

Planning & Engagement

3,393,000

(1,028,000)

2,365,000

Grand Total

$330,231,000

-

$330,231,000

 

Top Project Increases

Project ID and Name

2025 Adopted Budget

April 9th TBA

2025 Adjusted Budget

Rationale

SGR385 - Rail Replacement Work

$6,500,000

$5,500,000

$12,000,000

Funds for interlocking replacements at 450 East on Rice on the Red line

MSP999 - Capital Contingency

$5,000,000

$5,024,000

$10,024,000

Reduced by 10% that haven’t been reallocated yet.

SGR393 - Grade Crossing Program

$2,500,000

$3,000,000

$5,500,000

Increased to cover remaining planned costs for 2025 replacement efforts.

MSP262-SL Central HQ Office

$1,000,000

$1,652,000

$2,652,000

Increased funds to finish out the early design efforts for the project.

ICI214 - Automatic Passenger Counter Upgrade

$850,000

$1,350,000

$2,200,000

Increased funds to complete replacement project in 2025

ICI222 - Fares Systems Replacement Program

$4,996,000

$1,230,000

$6,226,000

Increased funds to complete contract milestones for 2025

ICI230 - Workforce/Enterprise Asset Management

$5,183,000

$1,000,000

$6,183,000

Increased funds to complete contract milestones for 2025

 

Top Project Decreases

Project ID and Name

2025 Adopted Budget

April 9th TBA

2025 Adjusted Budget

Rationale

REV238 - SD100/SD160 Light Rail Veh Rep

$35,400,000

$(5,400,000)

$30,000,000

Reduced due to extra 2025 funds when compared to contract milestones.

SGR370 - Red Light Signal Enforcement

$3,209,000

$(2,883,000)

$326,000

Project on Hold

FMA693 - Meadowbrook Electrification

$1,786,000

$(1,686,000)

$100,000

Funds moved and work will be completed under MidValley project

SGR397 - TPSS Component Replacement

$5,000,000

$(1,500,000)

$3,500,000

Project nearing completion - may need to add funds back at later date.

MSP258 - Mt. Ogden Admin Bldg Expansion

$7,713,000

$(1,357,000)

$6,356,000

Project still in design phase and contractor will be hired in Q4 2025 or Q1 2026

MSP259 - S-Line Expansion Project

$11,746,000

$(1,175,000)

$10,571,000

Subject to 10% reduction due to not hitting spend threshold.

ICI179 - Network & Infrastructure Equipment

$1,600,000

$(1,100,000)

$500,000

Funds moved to cover cost of other project needs - will look to refill in Q3 2025

MSP270 - Transit Signal Priority On Board Units (TOBU) Project

$1,711,000

$(1,011,000)

$700,000

Funds moved to cover costs of other project needs. Sufficient funding still available to cover obligations.

SGR040 - Light Rail Vehicle Rehab

$10,200,000

$(1,000,000)

$9,200,000

Funds moved to cover costs of other project needs. Sufficient funding still available to cover obligations.

SGR391 - Commuter Rail Vehicle Rehab/Replace

$3,000,000

$(1,000,000)

$2,000,000

Funds moved to cover costs of other project needs. Sufficient funding still available to cover obligations.

SGR403 - Train Control Rehab & Replacement

$8,000,000

$(1,000,000)

$7,000,000

Funds moved to cover costs of other project needs. Sufficient funding still available to cover obligations.

 

ALTERNATIVES:                                                                                                                                    

The following are options the Board could consider and the potential impacts of those decisions:

                     Board may reject the requested Technical Budget Adjustment.  The impact of this would be UTA would not be able to pay invoices that may come through for work that has been completed, or projects could be delayed due to lack of funding.

                     The Board may request revisions to the proposed Technical Budget Adjustment.  This could have the same impact as mentioned above. 

FISCAL IMPACT:                                                                                                                                

The proposed TBA of $26,073,000 will be funded by the approved 2025 Capital Budget.  Funds will be redistributed among the projects as described in the presentation and supplemental material contained within this packet.

If TBA is approved, there will be a balance remaining in the Capital Contingency of $10,024,000.  This TBA would add a net increase of $5,024,000 to the Contingency.  This net addition would be made up of additional funding sources including Bonds, Lease, State, and Local Partner funds.  The UTA Funds in the Contingency line were reduced from $5,000,000 to $3,800,000.

There is no increase in budget authority.  There is no impact on UTA’s Fund Balance. 

ATTACHMENTS:                                                                                                                                

                     TBA2025-03-01 Technical Budget Adjustment - Capital