Legislation Details

File #: 20-03349-55   
Type: Procurement Contract/Change Order Status: Passed
In control: Board of Trustees
On agenda: 4/27/2022 Final action: 4/27/2022
Title: Change Order: On-Call Infrastructure Maintenance Contract Task Order #22-55 - Garfield Tie and Ballast Replacement (Stacy and Witbeck, Inc)
Attachments: 1. On-Call Infrastructure Maintenance Contract Task Order #22-55 Garfield Tie and Ballast Replacement (Stacy and Witbeck, Inc)
Related files: 20-03349VW

TO:                

Board of Trustees

THROUGH:  

Jay Fox, Executive Director

FROM:          

Mary DeLoretto, Chief Service Development Officer

PRESENTER(S):

Jared Scarbrough, Acting Director of Capital Construction

 

Kyle Stockley, Rail Infrastructure Project Manager

 

TITLE:                                                                                                                                                                         

title

Change Order: On-Call Infrastructure Maintenance Contract Task Order #22-55 - Garfield Tie and Ballast Replacement (Stacy and Witbeck, Inc)

end

 

AGENDA ITEM TYPE:                                                                                                                        

Procurement Contract/Change Order

RECOMMENDATION:                                                                                                                       

Approve task order #22-55 to the on-call infrastructure maintenance contract with Stacy and Witbeck and authorize the Executive Director to execute the task order and associated disbursements  in the amount of $249,816.                     

BACKGROUND:                                                                                                                                 

In October 2020, UTA released a request for procurement (RFP) for an on-call maintenance contractor focused specifically on infrastructure assets.  Bids were received and evaluated, and Stacy and Witbeck Inc. was selected as the winner based on overall scoring using the best value format.  The UTA Board of Trustees approved the contract and authorized the Executive Director to execute the contract with Stacy and Witbeck Inc. on January 27, 2021.  This contract is for three-years with two one-year options. 

DISCUSSION:                                                                                                                                      

UTA has maintenance responsibilities for the Garfield Rail Corridor. This task order will  replace 800 ties and 280 tons of ballast on the Garfield line.  UTA Staff is requesting approval of this task order with Stacy and Witbeck, Inc. the amount of $249,816.00.

The task order has been determined to be within the scope of the master Task Ordering Agreement and the  pricing has been determined to be fair and reasonable based on both an  independent cost estimate and a price analysis.

CONTRACT SUMMARY:                                                                                                                   

Contractor Name:                          

Stacy and Witbeck Inc.

Contract Number:                          

20-03349-55

Base Contract Effective Dates:     

January 1, 2021 through December 31, 2023

Extended Contract Dates:            

N/A

Existing Contract Value:                

$17,347,331

Amendment Amount:                   

$249,816

New/Total Amount Contract Value:

$17,597,147

Procurement Method:                  

RFP best value modification

Funding Sources:                            

Capital project budget

 

 

ALTERNATIVES:                                                                                                                                    

Garfield line would not be maintained and UTA runs the risk of stopping freight service due to the line not meeting minimum FRA standards.

FISCAL IMPACT:                                                                                                                                

This budget is included in the 2022 Capital Program under project code: SGR401

ATTACHMENTS:                                                                                                                                

1)                     Task Order